The right to repossess or replevy unused materials from a jobsite will not be effective if
someone, in good faith, purchased it after removal from the site of the improvement. -
ANSWER✔✔-True.
The contractor must within _____ days after the receipt of the property owner's request,
furnishish to property owner or the property owner's agent a list of the subcontractors
and suppliers who have a contract with the contractor as of the date the request is
received by the contractor. - ANSWER✔✔-10 days.
A property perfected lien may be discharged by an order of the circuit court of the
_____ where the property is located. - ANSWER✔✔-county
When any interested party files a complaint, the clerk will issue a summons to the
lienor to show cause within _____ days why his or her lien should not to be enforced by
action or vacated and canceled of record. - ANSWER✔✔-20 days
COPYRIGHT © 2025 BY OLIVIA GREENWAYS, ALL RIGHTS RESERVED 1
, If a lienor fails to show cause why his or her lien should not be enforced or fails to start
such action before the return date of the summons, the court will immediately order
cancellation of the lien. - ANSWER✔✔-True
No lien provided by part 713.22 will continue for longer then ____ years after the claim
of lien has been recorded. - ANSWER✔✔-1 year
No lien provided by part 713.22 will continue for no longer then _______ years after the
recording of an amended claim of lien that shows a later date of final furnishing of
labor, services, or materials. - ANSWER✔✔-1 year
The lien of any lienor upon whom Notice of contest of Lien is served and who fails to
institute a suit to enforce his or her lien within ________ days after service of such notice
will be extinguished automatically. - ANSWER✔✔-60
The payment bond is required to ______ an owner under s. 713.23 must be furnished by
the contractor in at least the amount of the original contract price before commencing
the construction of the improvement under the direct contract. - ANSWER✔✔-exempt
A copy the payment bond must be attached to the Notice of Commencement when it is
_______. - ANSWER✔✔-recorded
Anyone who willfully files a fraudulent lien as defined in 713.31 commits a felony of the
______ degree - ANSWER✔✔-third
COPYRIGHT © 2025 BY OLIVIA GREENWAYS, ALL RIGHTS RESERVED 2
2025 | ALL QUESTIONS AND CORRECT ANSWERS |
GRADED A+ | LATEST EXAM | VERIFIED ANSWERS
The right to repossess or replevy unused materials from a jobsite will not be effective if
someone, in good faith, purchased it after removal from the site of the improvement. -
ANSWER✔✔-True.
The contractor must within _____ days after the receipt of the property owner's request,
furnishish to property owner or the property owner's agent a list of the subcontractors
and suppliers who have a contract with the contractor as of the date the request is
received by the contractor. - ANSWER✔✔-10 days.
A property perfected lien may be discharged by an order of the circuit court of the
_____ where the property is located. - ANSWER✔✔-county
When any interested party files a complaint, the clerk will issue a summons to the
lienor to show cause within _____ days why his or her lien should not to be enforced by
action or vacated and canceled of record. - ANSWER✔✔-20 days
COPYRIGHT © 2025 BY OLIVIA GREENWAYS, ALL RIGHTS RESERVED 1
, If a lienor fails to show cause why his or her lien should not be enforced or fails to start
such action before the return date of the summons, the court will immediately order
cancellation of the lien. - ANSWER✔✔-True
No lien provided by part 713.22 will continue for longer then ____ years after the claim
of lien has been recorded. - ANSWER✔✔-1 year
No lien provided by part 713.22 will continue for no longer then _______ years after the
recording of an amended claim of lien that shows a later date of final furnishing of
labor, services, or materials. - ANSWER✔✔-1 year
The lien of any lienor upon whom Notice of contest of Lien is served and who fails to
institute a suit to enforce his or her lien within ________ days after service of such notice
will be extinguished automatically. - ANSWER✔✔-60
The payment bond is required to ______ an owner under s. 713.23 must be furnished by
the contractor in at least the amount of the original contract price before commencing
the construction of the improvement under the direct contract. - ANSWER✔✔-exempt
A copy the payment bond must be attached to the Notice of Commencement when it is
_______. - ANSWER✔✔-recorded
Anyone who willfully files a fraudulent lien as defined in 713.31 commits a felony of the
______ degree - ANSWER✔✔-third