CSLB Concrete C8 License Practice Test #4
questions with answers
Which of the following tools is sufficient for the compacting of concrete in a
|| || || || || || || || || || || || ||
small project? - CORRECT ANSWERS ✔✔Hand tamper
|| || || || || || ||
At 50°F, how long should the concrete be protected to attain sufficient
|| || || || || || || || || || ||
strength (normally 500 Psi)? - CORRECT ANSWERS ✔✔48 Hours
|| || || || || || || || ||
Which of the following arrangements can be used to keep the concrete at the
|| || || || || || || || || || || || ||
recommended 50°F temperature for allowing proper setting? - CORRECT
|| || || || || || || || ||
ANSWERS ✔✔Heaters OR Thermal blankets
|| || || || ||
What is the 'Swell Factor' for sandy loam soil when performing excavation
|| || || || || || || || || || ||
work for a concrete structure? - CORRECT ANSWERS ✔✔About 1.1 to 1.2
|| || || || || || || || || || || ||
Which of the following building specification and cost estimating standard
|| || || || || || || || ||
systems is accepted as ASTM standard? - CORRECT ANSWERS ✔✔UniFormat
|| || || || || || || || || ||
System
||
Which of the following factors directly impact each other in the process of
|| || || || || || || || || || || ||
cost estimation for a concrete building project? - CORRECT ANSWERS
|| || || || || || || || || ||
✔✔Interest rate, Holding cost, Cost escalation
|| || || || || ||
,Which of the following points are true about Work Breakdown Structure
|| || || || || || || || || ||
(WBS) in the planning of a construction project? - CORRECT ANSWERS
|| || || || || || || || || || ||
✔✔Decomposing of a task into doable, measureable, estimable , and
|| || || || || || || || || ||
schedulable units
|| ||
Which of the following statements is correct about the finishing of a concrete?
|| || || || || || || || || || || ||
- CORRECT ANSWERS ✔✔Concrete should be finished once bleed water and
|| || || || || || || || || || ||
surface sheen disappear
|| || ||
An excavation of 10 cubic meters is done on any soil. Which of the following
|| || || || || || || || || || || || || ||
statements is true about the refilling volume of that excavation with the same
|| || || || || || || || || || || || ||
type of soil material? - CORRECT ANSWERS ✔✔More than 10 cubic meters
|| || || || || || || || || || || ||
What type of release oil is commonly used for the construction of wooden
|| || || || || || || || || || || ||
forms in the concrete industry? - CORRECT ANSWERS ✔✔Paraffin base oil
|| || || || || || || || || || ||
Initial and final setting time values of concrete are normally considered from:
|| || || || || || || || || || ||
- CORRECT ANSWERS ✔✔Mixing of water into cement material
|| || || || || || || || ||
Form-exposed corners and edges are commonly beveled to avoid any || || || || || || || || ||
chipping by using: - CORRECT ANSWERS ✔✔Chamfer strips
|| || || || || || || ||
Which of the following are the basic crafts used in estimating the concrete
|| || || || || || || || || || || ||
construction cost in the industry? - CORRECT ANSWERS ✔✔Ironworker,
|| || || || || || || || ||
Carpenter, Teamster, Cement mason
|| || || ||
, Which of the results of a concrete slump test has the highest workability? -
|| || || || || || || || || || || || ||
CORRECT ANSWERS ✔✔True Slump
|| || || ||
Explanation:
Workability is the ease or difficulty of placing concrete in a particular
|| || || || || || || || || || ||
location. For example, a stiff but plastic mix with large aggregate would be
|| || || || || || || || || || || || ||
workable in large open form but not in a wall with closely spaced
|| || || || || || || || || || || || ||
reinforcement. Please note that the slump test is NOT a measure of
|| || || || || || || || || || || ||
workability, and it should not be used to compare mixes of entirely different
|| || || || || || || || || || || || ||
proportions or containing different kinds of aggregate.
|| || || || || || ||
What is the maximum depth of a foundation footing commonly used in
|| || || || || || || || || || ||
concrete construction? - CORRECT ANSWERS ✔✔78"
|| || || || || ||
Which of the following factors should be estimated as earthwork components
|| || || || || || || || || ||
in project planning? - CORRECT ANSWERS ✔✔ALL OF THESE
|| || || || || || || || ||
-Rough grading, Excavation, Soil backfilling
|| || || ||
-Soil compacting, Fill material compacting, Excavation
|| || || || ||
-Excavated soil hauling, Soil backfilling, Rough grading
|| || || || || ||
According to American Concrete Institute ACI-301 standard, what is the
|| || || || || || || || ||
maximum volume of concrete that requires a strength test of concrete? -
|| || || || || || || || || || || ||
CORRECT ANSWERS ✔✔Each 100 cubic yards
|| || || || || ||
questions with answers
Which of the following tools is sufficient for the compacting of concrete in a
|| || || || || || || || || || || || ||
small project? - CORRECT ANSWERS ✔✔Hand tamper
|| || || || || || ||
At 50°F, how long should the concrete be protected to attain sufficient
|| || || || || || || || || || ||
strength (normally 500 Psi)? - CORRECT ANSWERS ✔✔48 Hours
|| || || || || || || || ||
Which of the following arrangements can be used to keep the concrete at the
|| || || || || || || || || || || || ||
recommended 50°F temperature for allowing proper setting? - CORRECT
|| || || || || || || || ||
ANSWERS ✔✔Heaters OR Thermal blankets
|| || || || ||
What is the 'Swell Factor' for sandy loam soil when performing excavation
|| || || || || || || || || || ||
work for a concrete structure? - CORRECT ANSWERS ✔✔About 1.1 to 1.2
|| || || || || || || || || || || ||
Which of the following building specification and cost estimating standard
|| || || || || || || || ||
systems is accepted as ASTM standard? - CORRECT ANSWERS ✔✔UniFormat
|| || || || || || || || || ||
System
||
Which of the following factors directly impact each other in the process of
|| || || || || || || || || || || ||
cost estimation for a concrete building project? - CORRECT ANSWERS
|| || || || || || || || || ||
✔✔Interest rate, Holding cost, Cost escalation
|| || || || || ||
,Which of the following points are true about Work Breakdown Structure
|| || || || || || || || || ||
(WBS) in the planning of a construction project? - CORRECT ANSWERS
|| || || || || || || || || || ||
✔✔Decomposing of a task into doable, measureable, estimable , and
|| || || || || || || || || ||
schedulable units
|| ||
Which of the following statements is correct about the finishing of a concrete?
|| || || || || || || || || || || ||
- CORRECT ANSWERS ✔✔Concrete should be finished once bleed water and
|| || || || || || || || || || ||
surface sheen disappear
|| || ||
An excavation of 10 cubic meters is done on any soil. Which of the following
|| || || || || || || || || || || || || ||
statements is true about the refilling volume of that excavation with the same
|| || || || || || || || || || || || ||
type of soil material? - CORRECT ANSWERS ✔✔More than 10 cubic meters
|| || || || || || || || || || || ||
What type of release oil is commonly used for the construction of wooden
|| || || || || || || || || || || ||
forms in the concrete industry? - CORRECT ANSWERS ✔✔Paraffin base oil
|| || || || || || || || || || ||
Initial and final setting time values of concrete are normally considered from:
|| || || || || || || || || || ||
- CORRECT ANSWERS ✔✔Mixing of water into cement material
|| || || || || || || || ||
Form-exposed corners and edges are commonly beveled to avoid any || || || || || || || || ||
chipping by using: - CORRECT ANSWERS ✔✔Chamfer strips
|| || || || || || || ||
Which of the following are the basic crafts used in estimating the concrete
|| || || || || || || || || || || ||
construction cost in the industry? - CORRECT ANSWERS ✔✔Ironworker,
|| || || || || || || || ||
Carpenter, Teamster, Cement mason
|| || || ||
, Which of the results of a concrete slump test has the highest workability? -
|| || || || || || || || || || || || ||
CORRECT ANSWERS ✔✔True Slump
|| || || ||
Explanation:
Workability is the ease or difficulty of placing concrete in a particular
|| || || || || || || || || || ||
location. For example, a stiff but plastic mix with large aggregate would be
|| || || || || || || || || || || || ||
workable in large open form but not in a wall with closely spaced
|| || || || || || || || || || || || ||
reinforcement. Please note that the slump test is NOT a measure of
|| || || || || || || || || || || ||
workability, and it should not be used to compare mixes of entirely different
|| || || || || || || || || || || || ||
proportions or containing different kinds of aggregate.
|| || || || || || ||
What is the maximum depth of a foundation footing commonly used in
|| || || || || || || || || || ||
concrete construction? - CORRECT ANSWERS ✔✔78"
|| || || || || ||
Which of the following factors should be estimated as earthwork components
|| || || || || || || || || ||
in project planning? - CORRECT ANSWERS ✔✔ALL OF THESE
|| || || || || || || || ||
-Rough grading, Excavation, Soil backfilling
|| || || ||
-Soil compacting, Fill material compacting, Excavation
|| || || || ||
-Excavated soil hauling, Soil backfilling, Rough grading
|| || || || || ||
According to American Concrete Institute ACI-301 standard, what is the
|| || || || || || || || ||
maximum volume of concrete that requires a strength test of concrete? -
|| || || || || || || || || || || ||
CORRECT ANSWERS ✔✔Each 100 cubic yards
|| || || || || ||