100% satisfaction guarantee Immediately available after payment Both online and in PDF No strings attached 4.2 TrustPilot
logo-home
Exam (elaborations)

TEST BANK For Information Technology Project Management 9th Edition by Kathy Schwalbe, Verified Chapters 1 - 13, Complete Newest Version

Rating
5.0
(2)
Sold
-
Pages
457
Grade
A+
Uploaded on
16-05-2025
Written in
2024/2025

TEST BANK For Information Technology Project Management 9th Edition by Kathy Schwalbe, Verified Chapters 1 - 13, Complete Newest Version True / False 1. Until the 1980s, project management primarily focused on providing schedule and resource data to top management in the military, computer, and construction industries. a. True b. False ANSWER: True RATIONALE: Feedback: Until the 1980s, project management primarily focused on providing schedule and resource data to top management in the military, computer, and construction industries. Today’s project management involves much more, and people in every industry and every country manage projects. POINTS: 1 DIFFICULTY: Difficulty: Easy REFERENCES: p.2 LEARNING OBJECTIVES: INFO.SCHW.14.1 - LO: 1-1 NATIONAL STANDARDS: United States - BUSPROG: Technology TOPICS: Introduction KEYWORDS: Bloom's: Knowledge 2. A difference between operations and projects is that operations end when their objectives have been reached, whereas projects do not. a. True b. False ANSWER: False RATIONALE: Feedback: Projects are different from operations in that they end when their objectives have been reached or the project has been terminated. POINTS: 1 DIFFICULTY: Difficulty: Moderate REFERENCES: p.4 LEARNING OBJECTIVES: INFO.SCHW.14.2 - LO: 1-2 NATIONAL STANDARDS: United States - BUSPROG: Analytic TOPICS: What is a Project? KEYWORDS: Bloom's: Comprehension 3. Every project should have a well-defined objective. a. True 2 Page 3 of 457 4. Projects should be developed in increments. a. True b. False ANSWER: True RATIONALE: Feedback: A project is developed using progressive elaboration. Projects are often defined broadly when they begin, and as time passes, the specific details of the project become clearer. Therefore, projects should be developed in increments. POINTS: 1 DIFFICULTY: Difficulty: Moderate REFERENCES: p.6 LEARNING OBJECTIVES: INFO.SCHW.14.2 - LO: 1-2 NATIONAL STANDARDS: United States - BUSPROG: Analytic TOPICS: What is a Project? KEYWORDS: Bloom's: Comprehensio

Show more Read less
Institution
Information Technology Project Management, 9e
Course
Information Technology Project Management, 9e











Whoops! We can’t load your doc right now. Try again or contact support.

Written for

Institution
Information Technology Project Management, 9e
Course
Information Technology Project Management, 9e

Document information

Uploaded on
May 16, 2025
Number of pages
457
Written in
2024/2025
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

Content preview

TEST BANK For Information Technology
Project Management 9th Edition
Kathy Schwalbe, Verified Chapters




Page 1 of 457

,True / False

1. Until the 1980s, project management primarily focused on providing schedule and resource data to top
management in the military, computer, and construction industries.
a. True
b. False
ANSWER: True
RATIONALE: Feedback: Until the 1980s, project management primarily focused on providing
schedule and resource data to top management in the military, computer, and
construction industries. Today’s project management involves much more, and
people in every industry and every country manage projects.
POINTS: 1
DIFFICULTY: Difficulty: Easy
REFERENCES: p.2
LEARNING OBJECTIVES: INFO.SCHW.14.1 - LO: 1-1
NATIONAL STANDARDS: United States - BUSPROG: Technology
TOPICS: Introduction
KEYWORDS: Bloom's: Knowledge


2. A difference between operations and projects is that operations end when their objectives have been
reached, whereas projects do not.
a. True
b. False
ANSWER: False
RATIONALE: Feedback: Projects are different from operations in that they end when their
objectives have been reached or the project has been terminated.
POINTS: 1
DIFFICULTY: Difficulty: Moderate
REFERENCES: p.4
LEARNING OBJECTIVES: INFO.SCHW.14.2 - LO: 1-2
NATIONAL STANDARDS: United States - BUSPROG: Analytic
TOPICS: What is a Project?
KEYWORDS: Bloom's: Comprehension


3. Every project should have a well-defined objective.
a. True




Page 2 of 457

,2



b. False
ANSWER: True
RATIONALE: Feedback: A project has a unique purpose. Every project should have a well-defined
objective.
POINTS: 1
DIFFICULTY: Difficulty: Easy
REFERENCES: p.6
LEARNING OBJECTIVES: INFO.SCHW.14.2 - LO: 1-2
NATIONAL STANDARDS: United States - BUSPROG: Analytic
TOPICS: What is a Project?
KEYWORDS: Bloom's: Knowledge


4. Projects should be developed in increments.
a. True
b. False
ANSWER: True
RATIONALE: Feedback: A project is developed using progressive elaboration. Projects are often
defined broadly when they begin, and as time passes, the specific details of the
project become clearer. Therefore, projects should be developed in increments.
POINTS: 1
DIFFICULTY: Difficulty: Moderate
REFERENCES: p.6
LEARNING OBJECTIVES: INFO.SCHW.14.2 - LO: 1-2
NATIONAL STANDARDS: United States - BUSPROG: Analytic
TOPICS: What is a Project?
KEYWORDS: Bloom's: Comprehension


5. Resources in a project should be used effectively because they are limited.
a. True
b. False
ANSWER: True
RATIONALE: Feedback: A project requires resources, often from various areas. Resources,
however, are limited and must be used effectively to meet project and other
corporate goals.
POINTS: 1
DIFFICULTY: Difficulty: Moderate
REFERENCES: p. 7
LEARNING OBJECTIVES: INFO.SCHW.14.2 - LO: 1-2
NATIONAL STANDARDS: United States - BUSPROG: Analytic
TOPICS: What is a Project?
KEYWORDS: Bloom's: Comprehension


Page 3 of 457

, 3



6. A project manager’s primary role is to provide the funding for a project.
a. True
b. False
ANSWER: False
RATIONALE: Feedback: A project sponsor usually provides the direction and funding for a project.
POINTS: 1
DIFFICULTY: Difficulty: Easy
REFERENCES: p.7
LEARNING OBJECTIVES: INFO.SCHW.14.2 - LO: 1-2
NATIONAL STANDARDS: United States - BUSPROG: Analytic
TOPICS: What is a Project?
KEYWORDS: Bloom's: Knowledge


7. One of the main reasons why project management is challenging is because of the factor of uncertainty.
a. True
b. False
ANSWER: True
RATIONALE: Feedback: A project involves uncertainty. Every project is unique and thus it is
sometimes difficult to define its objectives clearly, estimate how long it will take to
complete, or determine how much it will cost. This uncertainty is one of the main
reasons project management is so challenging.
POINTS: 1
DIFFICULTY: Difficulty: Moderate
REFERENCES: p.7
LEARNING OBJECTIVES: INFO.SCHW.14.2 - LO: 1-2
NATIONAL STANDARDS: United States - BUSPROG: Analytic
TOPICS: What is a Project?
KEYWORDS: Bloom's: Comprehension


8. Questions about how a team will track schedule performance is related to a project’s scope.
a. True
b. False
ANSWER: False
RATIONALE: Feedback: Project scope deals with questions such as, “What work will be done as
part of the project?”, “What unique product, service, or result does the customer or
sponsor expect from the project?”, or “How will the scope be verified?”
POINTS: 1
DIFFICULTY: Difficulty: Moderate
REFERENCES: p.7
LEARNING OBJECTIVES: INFO.SCHW.14.2 - LO: 1-2
NATIONAL STANDARDS: United States - BUSPROG: Technology


Page 3 of 457

Reviews from verified buyers

Showing all 2 reviews
4 months ago

5 months ago

5.0

2 reviews

5
2
4
0
3
0
2
0
1
0
Trustworthy reviews on Stuvia

All reviews are made by real Stuvia users after verified purchases.

Get to know the seller

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
BlessedNurse NURSING, ECONOMICS, MATHEMATICS, BIOLOGY, AND HISTORY MATERIALS BEST TUTORING, HOMEWORK HELP, EXAMS, TESTS, AND STUDY GUIDE MATERIALS WITH GUARANTEED A+ I am a dedicated medical practitioner with diverse knowledge in matters
View profile
Follow You need to be logged in order to follow users or courses
Sold
95
Member since
8 months
Number of followers
4
Documents
792
Last sold
3 days ago
BEST SELLER

EXCELLENCY IN ACCADEMIC MATERIALS ie exams, study guides, testbanks ,case, case study etc

5.0

209 reviews

5
208
4
1
3
0
2
0
1
0

Recently viewed by you

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Frequently asked questions