When erecting or stowing a swing-away lattice extension, what
should be used to control the movement of the extension? -
correct answer -Tag line
Planning for rigging is required: - correct answer -Only when lifting
any load
A lift plan MUST be completed by a: - correct answer -Supervisor
Anchorage points for fall arrest for a single person MUST be able
to hold: - correct answer -5000 lbs
Which of the following items are used for heavy rigging? - correct
answer -Slings, shackles, and spreader beam
, Page | 2
If the jacket of a synthetic round sling is damage, that sling should
be: - correct answer -Removed from service immediately
Which of the following is NOT a factor when making submerged
lifts? - correct answer -Water temu
When a tugger is mounted where the operator can NOT see the
load, the signal person MUST use: - correct answer -Signals used
for cranes
Who can design a personnel platform? - correct answer -A
qualified personnel
A one-inch, 3 leg bridle wire rope sling, rigged at 35' angle, is
good for 18 tons. The addition of a fourth leg will increase your
capacity by: - correct answer -0 lbs
After any structural repair of modification, a personnel lifting
platform shall be tested to what percentage of the platform rating?
- correct answer -150%
ADVANCED RIGGING 2025 BRAND
NEW ACTUAL EXAM WITH ANSWERS.
When erecting or stowing a swing-away lattice extension, what
should be used to control the movement of the extension? -
correct answer -Tag line
Planning for rigging is required: - correct answer -Only when lifting
any load
A lift plan MUST be completed by a: - correct answer -Supervisor
Anchorage points for fall arrest for a single person MUST be able
to hold: - correct answer -5000 lbs
Which of the following items are used for heavy rigging? - correct
answer -Slings, shackles, and spreader beam
, Page | 2
If the jacket of a synthetic round sling is damage, that sling should
be: - correct answer -Removed from service immediately
Which of the following is NOT a factor when making submerged
lifts? - correct answer -Water temu
When a tugger is mounted where the operator can NOT see the
load, the signal person MUST use: - correct answer -Signals used
for cranes
Who can design a personnel platform? - correct answer -A
qualified personnel
A one-inch, 3 leg bridle wire rope sling, rigged at 35' angle, is
good for 18 tons. The addition of a fourth leg will increase your
capacity by: - correct answer -0 lbs
After any structural repair of modification, a personnel lifting
platform shall be tested to what percentage of the platform rating?
- correct answer -150%