ENCE325 UPDATED ACTUAL Exam Questions and CORRECT Answers What are the primary ingredients of a contract? - CORRECT ANSWER agreement, Capacity, Consideration, Lawfulness - Mutual From an owners perspective a cost plus fee contract is the riskiest of all types of contracts. - CORRECT ANSWER - True One way to reduce owners risk is to have a cap on the contract of a project. This is an example of which type of contract? - CORRECT ANSWER - Cost Plus with a GMP

Content preview

MGRADES


ENCE325 UPDATED ACTUAL Exam
Questions and CORRECT Answers
What are the primary ingredients of a contract? - CORRECT ANSWER - Mutual
agreement, Capacity, Consideration, Lawfulness


From an owners perspective a cost plus fee contract is the riskiest of all types of contracts. -
CORRECT ANSWER - True


One way to reduce owners risk is to have a cap on the contract of a project. This is an example of
which type of contract? - CORRECT ANSWER - Cost Plus with a GMP



According to Dykstra what issues impact the choice of contract? - CORRECT ANSWER -
The project delivery method, Risk allocation, The quality of design information


The key to mutual agreement is that all parties agree to exactly what is written in the contract
documents. - CORRECT ANSWER - True


The following is an example of which type of contract? A contractor bids a fixed unit price and
the completion of work is paid based on actual quantities. - CORRECT ANSWER - Unit
Price


Contract documents include many components except which of the following? - CORRECT
ANSWER - Change Orders


Specifications complement drawings by answering several key information requirements. Select
all of the following applicable areas that specifications address. - CORRECT ANSWER -
Submittals, Quality of material and products and quality assurance, Special installation
requirements


General conditions are standards that can be used on multiple projects and are provided with the
agreement. General conditions outline and specify how many Key provisions including which of

, MGRADES


the following? - CORRECT ANSWER - Outline broad rights and responsibilities of the
parties, Outline terms for making changes to the work, Provide guidance for dealing with
disputes or delays, Specify the procedures for contractor payment


The agreement is one of the documents that make up a contract and is sometimes referred to as
the contract because it includes by reference all the other documents. - CORRECT
ANSWER - Address of the project and brief description of the work, List of documents
referenced by the agreement, Time for completion and contractor exclusions


GC's develop a rough schedule called a "big schedule" And as a part of preparing their bid. They
refine this as a "master construction schedule" with more detail after they are awarded the job. -
CORRECT ANSWER - True


There are many good reasons why scheduling is an important part of project management, as it
assists contractors in providing value in several ways except which of the following? -
CORRECT ANSWER - Drive subcontractor quality performance


Select all of the following types of schedules that are common in construction project
management. - CORRECT ANSWER - Bar charts, Network diagrams, Network bar charts


Select all of the following steps required to develop a master schedule. - CORRECT
ANSWER - Identify work activities, Sequence the work activities, Estimate activity
durations


The method by which activities are organized is called the Contractor Work Structure (CWS). -
CORRECT ANSWER - False, it's called a Work Breakdown Structure


An example of a software package relevant in project scheduling includes Primavera 6. -
CORRECT ANSWER - True


Preconstruction include several activities orchestrated by the project manager and superintendent
which of the following are considered pre-construction activities? - CORRECT
ANSWER - Job-site layout plan, Permits, Buying out the job, Adjusting the bid estimate

Document information

Uploaded on
May 9, 2025
Number of pages
9
Written in
2024/2025
Type
Exam (elaborations)
Contains
Questions & answers
$11.99

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
MGRADES
4.0
(235)
Sold
1539
Followers
108
Items
111937
Last sold
1 day ago



Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions