A full lot of super pave asphalt is what size?
1,000 tons
1,000 to 2000 tons
2000 to 4000 tons
1 days production - Correct answer-2000 to 4000 tons
Which is not typically used as an asphalt binder in fdot mix
designs?
PG 52-28
PG 58-22
PG 62-22
PG 76-22(PMA)
PG 82-22 (PMA) - Correct answer-PG 62-22
Who cuts the density cores used for verification testing?
The verification technician
, Page |2
The contractor
The independent verification testing technician
None of the above - Correct answer-The contractor
A full lot is composed of 5 sublots and 4 cores per lot T/F -
Correct answer-False
What is the most important for consistent compaction of asphalt
mix?
The mix is hotter in temperature
The mix is colder in temperature
The mix is uniform in temperature
Temperature of the mix does not affect compaction - Correct
answer-The mix is uniform in temperature
Referring to general stationing guidelines, R1 would be ____ than
R2
Closer to centerline
ASPHALT PAVING LEVEL 1 2025
QUESTIONS AND ANSWERS.
A full lot of super pave asphalt is what size?
1,000 tons
1,000 to 2000 tons
2000 to 4000 tons
1 days production - Correct answer-2000 to 4000 tons
Which is not typically used as an asphalt binder in fdot mix
designs?
PG 52-28
PG 58-22
PG 62-22
PG 76-22(PMA)
PG 82-22 (PMA) - Correct answer-PG 62-22
Who cuts the density cores used for verification testing?
The verification technician
, Page |2
The contractor
The independent verification testing technician
None of the above - Correct answer-The contractor
A full lot is composed of 5 sublots and 4 cores per lot T/F -
Correct answer-False
What is the most important for consistent compaction of asphalt
mix?
The mix is hotter in temperature
The mix is colder in temperature
The mix is uniform in temperature
Temperature of the mix does not affect compaction - Correct
answer-The mix is uniform in temperature
Referring to general stationing guidelines, R1 would be ____ than
R2
Closer to centerline