July 1 2005, service techs shall possess or work under someone who has a current certification
indicating he or she has passed the ? - (ANSWER)California UST service technician exam
ICC cert must be renewed every? - (ANSWER)24 months
Service techs must posses or be employed by a person who has the appropriate contractors
license unless? - (ANSWER)The individual has a Tank testing licens
Service tech is defined by any individual who? - (ANSWER)Test UST monitoring equipment
Trouble shoots UST systems
Installs UST monitoring equipment
If the manufacturer training no longer exist , the local angency may? - (ANSWER)Approve
comparable alternat training .
UST includes? - (ANSWER)Tank and connected piping
What is considered and UST - (ANSWER)petroleum storage tank
What UST system meets the requirements for secondary containment? - (ANSWER)Doubled
wall tanks
According to title 23; the following piping components if installed after July 1 1987 must have
secondary containment - (ANSWER)Pressured product piping
, Considered "pipe" on tanks installed after July 1 2003 - (ANSWER)Pressured product piping
and below ground vapor recovery
Under dispenser containment (UDC) was required for all UST systems by -
(ANSWER)December 31 2003
System for exchanging gas vapors in a storage tank and product in a fuel delivery truck -
(ANSWER)Stage 1 vapor recovery
An approved method for non visual monitoring for existing UST systems. -
(ANSWER)Statistical Inventory Reconciliation (SIR)
ATG must be capable for detecting a release of ? - (ANSWER).2 gallons per hour
Manual inventory reconciliation. - (ANSWER)No longer an approved method for non visual
monitoring on existing UST systems
Automatic line leak detectors installed on underground piping with secondary containment shall
be capable of tetecting a leak of ? - (ANSWER)3 gallons per hour at 10 psi
ATG should be programmed to test the tank ? - (ANSWER)At least monthly
According to PEI RP 300 a combustible gas can be used to ? - (ANSWER)Detect vapor leaks in
a vapor recovery system.
According to PEI RP 300. A written scope of work for vapor recovery installation should
include? - (ANSWER)Construction plans
WITH 100% RATED CORRECT ANSWERS (ACCURATELY PASSED)
2025 LATEST UPDATED GET A+
July 1 2005, service techs shall possess or work under someone who has a current certification
indicating he or she has passed the ? - (ANSWER)California UST service technician exam
ICC cert must be renewed every? - (ANSWER)24 months
Service techs must posses or be employed by a person who has the appropriate contractors
license unless? - (ANSWER)The individual has a Tank testing licens
Service tech is defined by any individual who? - (ANSWER)Test UST monitoring equipment
Trouble shoots UST systems
Installs UST monitoring equipment
If the manufacturer training no longer exist , the local angency may? - (ANSWER)Approve
comparable alternat training .
UST includes? - (ANSWER)Tank and connected piping
What is considered and UST - (ANSWER)petroleum storage tank
What UST system meets the requirements for secondary containment? - (ANSWER)Doubled
wall tanks
According to title 23; the following piping components if installed after July 1 1987 must have
secondary containment - (ANSWER)Pressured product piping
, Considered "pipe" on tanks installed after July 1 2003 - (ANSWER)Pressured product piping
and below ground vapor recovery
Under dispenser containment (UDC) was required for all UST systems by -
(ANSWER)December 31 2003
System for exchanging gas vapors in a storage tank and product in a fuel delivery truck -
(ANSWER)Stage 1 vapor recovery
An approved method for non visual monitoring for existing UST systems. -
(ANSWER)Statistical Inventory Reconciliation (SIR)
ATG must be capable for detecting a release of ? - (ANSWER).2 gallons per hour
Manual inventory reconciliation. - (ANSWER)No longer an approved method for non visual
monitoring on existing UST systems
Automatic line leak detectors installed on underground piping with secondary containment shall
be capable of tetecting a leak of ? - (ANSWER)3 gallons per hour at 10 psi
ATG should be programmed to test the tank ? - (ANSWER)At least monthly
According to PEI RP 300 a combustible gas can be used to ? - (ANSWER)Detect vapor leaks in
a vapor recovery system.
According to PEI RP 300. A written scope of work for vapor recovery installation should
include? - (ANSWER)Construction plans