CON 3910 EXAM (QUESTIONBANK) 326
QUESTIONS WITH ACCURATE
SOLUTIONS!!
, Don't know?
2 of 326
Term
What are the seven statutory authorities that permit contracting
without providing for full and open competition (Other Than Full and
Open Competition):
Give this one a try later!
1. Only one responsible source and no other supplies or services will satisfy
agency requirements
2. Unusual and compelling urgency
3. Industrial mobilization; engineering, developmental, or research
capability; or expert services
4. International Agreement
5. Authorized or required by statute
6. National Security
7. Public Interest
1. "Sources Sought" solicitation
2. Request for Information (RFI) distribution
3. Pre-Solicitation Conference or Industry Day
4. One-on-one interactions
5. Solicitation of feedback on Draft RFP
, - Two or more responsible offerors, competing independently, submit offers that
satisfy Government requirements
- Award will be made to offeror whose proposal represents the best value
- No finding that the price of the otherwise successful offeror is unreasonable.
- Industry or small business conferences
- Public Hearings
- Market Research
- One-on-one meetings with potential offerors
- Pre-Solicitation Notices
- Draft Requests for Proposals (RFP)
- Request For Information (RFI's)
- Pre-Solicitation or Pre-Proposal conferences
- Site visits
Don't know?
3 of 326
Term
Calendar day, unless specified otherwise.
Give this one a try later!
Week Day
Month Year
Don't know?
, 4 of 326
Term
When amending a Request for Proposal, amendments issued before
the established time and date for reciept of RFPs must?
Amendments issued after the established time and date for receipt
of RFPS must?
Give this one a try later!
1) Promote full and open competition
2) Minimize restrictive provisions
3) State requirements in terms of function, performance, and physical
characteristics
- Review facts pertinent to claim
- Secure assistance from legal and other advisors
- Coordinate with CAO or contracting office as appropriate
- Prepare a written decision
The KO shall immediately suspend performance, pending resolution of the
protest within the agency- UNLESS continued performance is justified, in writing,
for urgent and compelling reasons or is determined, in writing, to be in the best
interest of the Government.
- Amendments issued before established time and date for receipt of
proposals, must be issued to all parties receiving the solicitation.
- Amendments issued after established time and date for receipt of
proposals, must be issued to all offerors that have not been eliminated
from competition.
QUESTIONS WITH ACCURATE
SOLUTIONS!!
, Don't know?
2 of 326
Term
What are the seven statutory authorities that permit contracting
without providing for full and open competition (Other Than Full and
Open Competition):
Give this one a try later!
1. Only one responsible source and no other supplies or services will satisfy
agency requirements
2. Unusual and compelling urgency
3. Industrial mobilization; engineering, developmental, or research
capability; or expert services
4. International Agreement
5. Authorized or required by statute
6. National Security
7. Public Interest
1. "Sources Sought" solicitation
2. Request for Information (RFI) distribution
3. Pre-Solicitation Conference or Industry Day
4. One-on-one interactions
5. Solicitation of feedback on Draft RFP
, - Two or more responsible offerors, competing independently, submit offers that
satisfy Government requirements
- Award will be made to offeror whose proposal represents the best value
- No finding that the price of the otherwise successful offeror is unreasonable.
- Industry or small business conferences
- Public Hearings
- Market Research
- One-on-one meetings with potential offerors
- Pre-Solicitation Notices
- Draft Requests for Proposals (RFP)
- Request For Information (RFI's)
- Pre-Solicitation or Pre-Proposal conferences
- Site visits
Don't know?
3 of 326
Term
Calendar day, unless specified otherwise.
Give this one a try later!
Week Day
Month Year
Don't know?
, 4 of 326
Term
When amending a Request for Proposal, amendments issued before
the established time and date for reciept of RFPs must?
Amendments issued after the established time and date for receipt
of RFPS must?
Give this one a try later!
1) Promote full and open competition
2) Minimize restrictive provisions
3) State requirements in terms of function, performance, and physical
characteristics
- Review facts pertinent to claim
- Secure assistance from legal and other advisors
- Coordinate with CAO or contracting office as appropriate
- Prepare a written decision
The KO shall immediately suspend performance, pending resolution of the
protest within the agency- UNLESS continued performance is justified, in writing,
for urgent and compelling reasons or is determined, in writing, to be in the best
interest of the Government.
- Amendments issued before established time and date for receipt of
proposals, must be issued to all parties receiving the solicitation.
- Amendments issued after established time and date for receipt of
proposals, must be issued to all offerors that have not been eliminated
from competition.