Which of the following should happen when an automatic fire sprinkler system in
an occupied hospital is out of service more than 10 hours in a 24 hour period?
A. The Authority Having Jurisdiction (AHJ) shall be notified and a hospital wide
announcement shall be made.
B. The Authority Having Jurisdiction (AHJ) shall be notified and a fire watch shall be
put into action.
C. The hospital insurance company shall be notified.
D. The fire department shall be notified. - ✔✔B. The Authority Having Jurisdiction
shall be notified and a fire watch shall be put in place by the hospital whenever an
occupied portion of the hospital's automatic fire sprinkler system is out of service for
more than 10 hours. The hospital should also notify its insurance provider.
(NFPA 25 2011 Edition 15.5.2 (4))
ISO 9001 is what kind of system?
COPYRIGHT © 2025 BY SOPHIA BENNETT, ALL RIGHTS RESERVED 1
,A. Quality Management System
B. Lean System
C. Safety Management System
D. None of the above - ✔✔A. ISO 9001 is a Quality Management System that has a
focus on risk based thinking.
When planning for new, altered, or renovated space, the hospital uses which of the
following design criteria?
A. Standards for local construction
B. National Institute of Architects design recommendations
C. Guidelines for Design and Construction of Hospitals and Health Care Facilities
D. National Electrical Code - ✔✔C. The hospital must use the latest edition of the
Guidelines for Design and Construction of Hospitals and Health Care Facilities
published by the American Institute of Architects. The hospital must also meet all of
its state rules and regulations.
The ISO standards are owned by who?
COPYRIGHT © 2025 BY SOPHIA BENNETT, ALL RIGHTS RESERVED 2
,A. The Joint Commission
B. DNV
C. International Standards Organization
D. International Organization for Standardization - ✔✔The ISO standards are owned
by The International Organization for Standardization
When planning for construction, demolition, or renovation, the hospital conducts a
pre-construction risk assessment for all of the following except:
A. Air quality
B. Infection control
C. Noise
D. Time frame for project completion - ✔✔D. The hospital must perform a pre-
construction risk assessment before any construction, renovation, or demolition that
should address noise, vibration, dust, air quality, infection control, egress and all
areas of Life Safety.
The ISO 9001 standards force hospitals to become what?
A. Compliant
COPYRIGHT © 2025 BY SOPHIA BENNETT, ALL RIGHTS RESERVED 3
, B. Risk free
C. Consistent
D. None of the above - ✔✔C. ISO 9001 forces hospitals to become consistent
The key to successfully managing the physical environment in a hospital is:
A. A good ISLM (Interim Life Safety Measure)
B. A complete PCRA (Pre-Construction Risk Assessment)
C. Properly trained people
D. A good EOC (Environment of Care) Committee - ✔✔C. Properly trained people
are the key to managing the physical environment in a hospital. Plans and policies
are worthless without people who understand and follow them.
The hospital establishes a process for continually monitoring, internally reporting
and investigating utilities systems management problems, failures, and errors.
Which of the following would be an example of a utility failure that must be
internally reported and investigated?
A. Loss of electric to the main conference room