Written by students who passed Immediately available after payment Read online or as PDF Wrong document? Swap it for free 4.6 TrustPilot
logo-home
Document preview thumbnail
Preview 4 out of 76 pages
Exam (elaborations)

IRC TEST FULL EXAM ACTUAL EXAM QUESTIONS AND CORRECT DETAILED ANSWERS (VERIFIED ANSWERS) |ALREADY GRADED A+||BRAND NEW!! 2025

Document preview thumbnail
Preview 4 out of 76 pages

IRC TEST FULL EXAM ACTUAL EXAM QUESTIONS AND CORRECT DETAILED ANSWERS (VERIFIED ANSWERS) |ALREADY GRADED A+||BRAND NEW!! 2025

Content preview

IRC TEST FULL EXAM ACTUAL EXAM QUESTIONS AND CORRECT DETAILED ANSWERS
(VERIFIED ANSWERS) |ALREADY GRADED A+||BRAND NEW!! 2025

The International Residential Code is applicable to single-family dwellings a maximum of
_______________ stories in above-grade-plane height.

A. One

B. Two

C. Three

D. Four - (ANSWER)C
@#$%%$
)(*&^
#$%^
If there is a conflict in the code between a general requirement and a specific requirement,
the _______________ requirement shall apply.
@#$%^&
A. General
*(*&^%
B. Specific

C. Least restrictive

D. Most restrictive - (ANSWER)B



Provisions of the appendices do not apply unless _______________.

A. Specified in the code

B. Applicable to unique conditions

C. Specifically adopted

D. Relevant to fire or life safety - (ANSWER)C



_______________ is the term used in the IRC to describe the individual in charge of the
department of building safety.

A. Building official

B. Code official

C. Code administrator

D. Chief building inspector - (ANSWER)A

, IRC TEST FULL EXAM ACTUAL EXAM QUESTIONS AND CORRECT DETAILED ANSWERS
(VERIFIED ANSWERS) |ALREADY GRADED A+||BRAND NEW!! 2025

The building official has the authority to _______________ the provisions of the code.

A. Ignore

B. Waive

C. Violate

D. Interpret - (ANSWER)D


@#$%%$
Used materials may be utilized under which one of the following conditions? )(*&^
#$%^
A. They meet the requirements for new materials

B. When approved by the building official @#$%^&
C. Used materials may never be used in new construction *(*&^%

D. A representative sampling is tested for compliance - (ANSWER)B



The building official has the authority to grant modifications to the code _______________.

A. for only those issues not affecting life safety or fire safety

B. for individual cases where the strict letter of the code is impractical

C. where the intent and purpose of the code cannot be met

D. related only to administrative functions - (ANSWER)B



Unless supporting a surcharge, retaining walls having a maximum height of __________
inches, measured from the bottom of the footing to the top of the wall, do not require a
permit.

A. 30

B. 36

C. 48

D. 60 - (ANSWER)C

, IRC TEST FULL EXAM ACTUAL EXAM QUESTIONS AND CORRECT DETAILED ANSWERS
(VERIFIED ANSWERS) |ALREADY GRADED A+||BRAND NEW!! 2025

Tests performed by _______________ may be required by the building official where there is
insufficient evidence of code compliance.

A. The owner

B. The contractor

C. An approved agency

D. A design professional - (ANSWER)C
@#$%%$
)(*&^
#$%^
A permit is not required for the construction of a one-story detached accessory structure
when it has a maximum floor area of _______________ square feet.
@#$%^&
A. 100
*(*&^%
B. 120

C. 150

D. 200 - (ANSWER)D



Prefabricated swimming pools are subject to a building permit where they have a minimum
depth of _______________ .

A. 12 inches

B. 24 inches

C. 30 inches

D. 36 inches - (ANSWER)B



Unless an extension is authorized, a permit becomes invalid when work does not
commence within _______________ after permit issuance.

A. 90 days

B. 180 days

C. one year

D. two years - (ANSWER)B

, IRC TEST FULL EXAM ACTUAL EXAM QUESTIONS AND CORRECT DETAILED ANSWERS
(VERIFIED ANSWERS) |ALREADY GRADED A+||BRAND NEW!! 2025



The building permit, or a copy of the permit, shall be kept _______________ until completion
of the project.

A. At the job site

B. By the permit applicant

C. By the contractor

D. By the owner - (ANSWER)A @#$%%$
)(*&^
#$%^


When a building permit is issued, the construction documents shall be approved
@#$%^&
_______________.
*(*&^%
A. In writing or by stamp

B. And two sets returned to the applicant

C. And stamped as "Accepted as Reviewed"

D. Pending payment of the plan review fee - (ANSWER)A



Unless otherwise mandated by state or local laws, the approved construction documents
shall be retained by the building official for a minimum of _______________ from the date of
completion of the permitted work.

A. 90 days

B. 180 days

C. one year

D. two years - (ANSWER)B



Where applicable, which one of the following inspections is not specifically identified by
the International Residential Code as a required inspection?

A. Foundation inspection

B. Frame inspection

Document information

Uploaded on
April 12, 2025
Number of pages
76
Written in
2024/2025
Type
Exam (elaborations)
Contains
Questions & answers
$15.08

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
QuickFixer
3.6
(19)
Sold
2074
Followers
7
Items
1202
Last sold
2 weeks ago

Reviews from verified buyers




Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions