Order of inspections - 1: forms, basement and crawlspace 2: Plumbing, dampproofing, foundation drainage , sanitary sewer, storm sewer, sump, water service 3: plumbing, electrical, mechanical, gas 4: framing inspection 5: insulation and vapour barrier 6: rainscreen/exterior finishs, drywall 7: building envelop inspection 8: final inspection Which is not an acceptable method for determining the correct grading for a trench? - An experienced excavator says it's ok At what depth is shoring required? - 1.2m/4ft Which best describes the principle of rain waterterm-0 deflection? - Design and construction that prevents water from ever entering What lighting safety certifications are required in Canada? - CSA safety certification What grit of sandpaper would get the smoothest result? - Higher grit with get a smoother finish What is the maximum rise in a flight of stairs? - The vertical height of any flight of stairs should not exceed 3.7m What is the minimum distance that a ladder must extend above a parapet wall or landing? - 3ft

Content preview

BC Owner Builder Exam



BC Owner Builder Exam Questions and
Answers
Order of inspections - 1: forms, basement and crawlspace
2: Plumbing, dampproofing, foundation drainage , sanitary sewer, storm sewer,
sump, water service
3: plumbing, electrical, mechanical, gas
4: framing inspection
5: insulation and vapour barrier
6: rainscreen/exterior finishs, drywall
7: building envelop inspection
8: final inspection


Which is not an acceptable method for determining the correct grading for a
trench? - An experienced excavator says it's ok


At what depth is shoring required? - 1.2m/4ft


Which best describes the principle of rain waterterm-0 deflection? - Design and
construction that prevents water from ever entering


What lighting safety certifications are required in Canada? - CSA safety
certification




BC Owner Builder Exam

,BC Owner Builder Exam


What grit of sandpaper would get the smoothest result? - Higher grit with get a
smoother finish


What is the maximum rise in a flight of stairs? - The vertical height of any flight of
stairs should not exceed 3.7m


What is the minimum distance that a ladder must extend above a parapet wall or
landing? - 3ft


What heights are end dams to be on windows and door flashings? - 25mm/1 inch


End dam use - Stop water from coming in


When should you call for inspectors to make them efficient as possible? - Group
inspectors together when possible and call when work is complete


When is an HRV required? - Almost always


What can you build under the owner-builder HPO process? - Single detached home
under a single title. Single dwelling attached to pre-existing building older than 10
years. Single dwelling attached to a new non-residential building.


Who issues permits for a gas fireplace? - Safety Authority (call Technical Safe BC)


Can an owner builder take out their own electrical permit? - Yes, up to 200A


BC Owner Builder Exam

, BC Owner Builder Exam


What is the best way to apply asphalt waterproofing on a foundation? - Spray-on or
roll on dry foundation with 2in. below grade


When is the appropriate time to backfill a foundation? - After damp-proofing


What do you need to do when applying a peel and stick waterproof membrane
foundation? - Use an approved primer before installing


What are gas meter installation requirements? - The distance from the gas vent to
the roof must be greater than the overhang of the roof, nothing can be with in 1m
either side or 4.5m above a gas meter


When do you need to install a handrail or have fall protection? - 10ft, 4ft if no fall
protection


How high does a construction fence around a site need to be? - 6ft


When installing the footer, it was dug down 2in. deeper than what the elevation
should be. What needs to happen? - Install the footing form at proper elevation and
fill with extra concrete


When installing flashing for a roof valley how much do the asphalt shingles need
to overlap? - 6in.


What would cause a blister on a flat roof? - Moisture trapped under roof



BC Owner Builder Exam

Document information

Uploaded on
April 1, 2025
Number of pages
20
Written in
2024/2025
Type
Exam (elaborations)
Contains
Questions & answers
$12.99

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
Lectsavvy
4.1
(17)
Sold
94
Followers
39
Items
3668
Last sold
3 months ago



Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions