Exam (elaborations)

Construction Management on scheduling (e.g., CPM and PERT) 3Construction Management on scheduling (e.g., CPM and PERT) 3

Document preview thumbnail
Preview 4 out of 38 pages

Construction Management on scheduling (e.g., CPM and PERT) 3

Content preview

1. In PERT, if the optimistic time is 4 days, the most likely time is 8 days, and the

pessimistic time is 12 days, what is the expected time for the activity?

A. 8 days

B. 6.67 days

C. 7 days

D. 10 days

Answer: B) 6.67 days

Rationale and Working Out:

Using the formula for expected time in PERT:

TE=O+4M+P6TE = \frac{O + 4M + P}{6}TE=6O+4M+P

Where:

• O = Optimistic time = 4

• M = Most likely time = 8

• P = Pessimistic time = 12

TE=4+4(8)+126=4+32+126=486=8 days.TE = \frac{4 + 4(8) + 12}{6} = \frac{4 + 32

+ 12}{6} = \frac{48}{6} = 8 \text{ days}.TE=64+4(8)+12=64+32+12=648=8 days.

,2. Which of the following is an advantage of using the PERT technique over CPM?

A. It focuses more on time estimates and scheduling.

B. It requires fewer resources to develop.

C. It handles uncertainty by using probabilistic time estimates.

D. It gives more accurate cost projections.

Answer: C) It handles uncertainty by using probabilistic time estimates.

Rationale:

PERT is better suited for projects with uncertainty in time estimates, as it uses

probabilistic estimates (optimistic, pessimistic, and most likely).




3. Which of the following activities is most likely to require PERT instead of CPM?

A. A construction project with well-defined tasks and time estimates.

B. A new research and development project with uncertain activity durations.

C. A manufacturing project with fixed durations.

D. A software development project with known task durations.

Answer: B) A new research and development project with uncertain activity

durations.

Rationale:

,PERT is ideal for projects with uncertain or variable durations, like R&D, where time

estimates are less predictable.




4. In PERT analysis, if the optimistic time is 3 days, the most likely time is 5 days,

and the pessimistic time is 7 days, what is the expected time for the activity?

A. 5 days

B. 4 days

C. 5.5 days

D. 4.33 days

Answer: D) 4.33 days

Rationale and Working Out:

Using the PERT formula for expected time:

TE=O+4M+P6TE = \frac{O + 4M + P}{6}TE=6O+4M+P

Where:

• O = Optimistic time = 3

• M = Most likely time = 5

• P = Pessimistic time = 7

TE=3+4(5)+76=3+20+76=306=5 days.TE = \frac{3 + 4(5) + 7}{6} = \frac{3 + 20 +

7}{6} = \frac{30}{6} = 5 \text{ days}.TE=63+4(5)+7=63+20+7=630=5 days.

, 5. Which of the following statements is TRUE about the float (slack) in a project

schedule?

A. Float is the time an activity can be delayed without delaying the project

completion.

B. Float is the time an activity can be delayed without affecting the critical path.

C. Float is always zero on the critical path.

D. Float is always positive on all activities.

Answer: C) Float is always zero on the critical path.

Rationale:

Activities on the critical path have zero float because any delay will directly impact

the project's overall completion time. Activities not on the critical path may have float

and can be delayed without affecting the project’s final duration.




6. What is the purpose of the forward pass in CPM scheduling?

A. To determine the project’s finish date.

B. To calculate the float for each activity.

C. To calculate the latest start and finish times.

D. To determine the earliest start and finish times for each activity.

Document information

Uploaded on
March 16, 2025
Number of pages
38
Written in
2024/2025
Type
Exam (elaborations)
Contains
Questions & answers
$10.99

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Seller avatar
douglasmugwe82
5.0
(1)
Sold
2
Followers
0
Items
4217
Last sold
1 year ago



Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions