Walmart - Stormwater Exam Questions ANd
Answers
The 1970's law that set into place the regulation of stormwater is: -
--
correct answer ✅The Clean Water Act
Requirements for managing stormwater activity on a construction
site are outlined in the following regulation: - - -
correct answer ✅NPDES
Which of the following is never an allowable stormwater discharge
from a construction site? - - -
correct answer ✅Discharge from contaminated groundwater
The Notice of termination can filed when: - - -
correct answer ✅All construction activity, inside and outside the
building, is complete and permanent stabilization verified
Relative to stormwater permitting, all of the following must occur
before construction starts except: - - -
correct answer ✅Submit the notice of termination (NOT)
Which erosion control best mgmt practice increases water
infiltration, dissipates rainfall energy and slows overland flow of
, Walmart - Stormwater Exam Questions ANd
Answers
stormwater - - -
correct answer ✅Vegetation
Of the following factors that influence erosion rates, the one a
contractor has the most control over is: - - -
correct answer ✅Groundcover
Temporary stabilization should be implemented - - -
correct answer ✅Immediately on all disturbed areas that are likely
to or will remain inactive for 14-days or more
The Primary purpose of a construction exit is - - -
correct answer ✅To remove sediment from construction site
vehicles and minimize trackout
Common types of erosion include all of the following except - - -
correct answer ✅Sedimentation
Which of the following is NOT a beneficial use of water? - - -
correct answer ✅Flushing a spill down a storm drain
Answers
The 1970's law that set into place the regulation of stormwater is: -
--
correct answer ✅The Clean Water Act
Requirements for managing stormwater activity on a construction
site are outlined in the following regulation: - - -
correct answer ✅NPDES
Which of the following is never an allowable stormwater discharge
from a construction site? - - -
correct answer ✅Discharge from contaminated groundwater
The Notice of termination can filed when: - - -
correct answer ✅All construction activity, inside and outside the
building, is complete and permanent stabilization verified
Relative to stormwater permitting, all of the following must occur
before construction starts except: - - -
correct answer ✅Submit the notice of termination (NOT)
Which erosion control best mgmt practice increases water
infiltration, dissipates rainfall energy and slows overland flow of
, Walmart - Stormwater Exam Questions ANd
Answers
stormwater - - -
correct answer ✅Vegetation
Of the following factors that influence erosion rates, the one a
contractor has the most control over is: - - -
correct answer ✅Groundcover
Temporary stabilization should be implemented - - -
correct answer ✅Immediately on all disturbed areas that are likely
to or will remain inactive for 14-days or more
The Primary purpose of a construction exit is - - -
correct answer ✅To remove sediment from construction site
vehicles and minimize trackout
Common types of erosion include all of the following except - - -
correct answer ✅Sedimentation
Which of the following is NOT a beneficial use of water? - - -
correct answer ✅Flushing a spill down a storm drain