• Wrong document? Swap it for free
  • Written by students who passed
  • Immediately available after payment
  • Read online or as PDF
Sell
Where do you study
Your language
Document preview thumbnail
Preview 4 out of 33 pages
Exam (elaborations)

Fac-C Certification Exam Notes 7

Document preview thumbnail
Preview 4 out of 33 pages

FAC-C CERTIFICATION EXAM NOTES 7

Content preview

1. Which of the following best describes a "Purchase Order" in
federal contracting?
A. A legally binding agreement for a contract award
B. A contract for the procurement of goods and services under
$25,000
C. A written document used to order supplies from a contractor
D. A document issued when a contract has been terminated
Answer: C) A written document used to order supplies from a
contractor
Rationale: A Purchase Order is a written document issued by a
government agency to a contractor to order goods or services. It
is commonly used for small acquisitions under the simplified
acquisition threshold.


2. Which of the following is a key principle of the Federal
Acquisition System?
A. Minimizing competition to save time
B. Maximizing transparency and competition
C. Simplifying all contract processes for contractors
D. Awarding contracts only to the lowest bidder
Answer: B) Maximizing transparency and competition

,Rationale: The Federal Acquisition System emphasizes
maximizing competition and transparency to ensure fair and
efficientcontracting processes. This helps ensure that the
government receives the best value and that all suppliers have
equal opportunity to compete.


3. Which of the following is a typical feature of a "Time and
Materials" (T&M) contract?
A. A fixed price is agreed upon upfront.
B. The contractor is reimbursed for materials and labor costs, plus
a fee.
C. The contract is used exclusively for research and development.
D. The contract involves a set deliverable with specific deadlines.
Answer: B) The contractor is reimbursed for materials and labor
costs, plus a fee.
Rationale: A T&M contract reimburses the contractor for direct
labor and materials costs, with an additional fee or markup. It is
often used when the scope of work is uncertain and difficult to
define in advance.


4. Under the FAR, which of the following is the preferred method
of procurement for supplies and services that can be clearly
defined?
A. Sole-source contracting
B. Simplified Acquisition Procedures (SAP)

,C. Competitive bidding
D. Cost-reimbursement contracting
Answer: C) Competitive bidding
Rationale: Competitive bidding is the preferred method for
procurement when the requirements can be clearly defined,
ensuring competition and the best possible price.


5. Which of the following best describes "overhead costs" in the
context of federal contracts?
A. The costs associated with direct materials and labor
B. Costs that are incurred for activities that cannot be directly
attributed to a specific contract, such as administrative support
C. Costs that are excluded from government contracts
D. Costs related to the delivery and transportation of goods
Answer: B) Costs that are incurred for activities that cannot be
directly attributed to a specific contract, such as administrative
support
Rationale: Overhead costs include expenses that are necessary for
the general operation of the business but are not directly
assignable to a specific project or contract.


6. What is the main purpose of the "Federal Awardee Performance
and Integrity Information System" (FAPIIS)?

, A. To evaluate contractors' past performance during the proposal
stage
B. To provide a database of contractors' financial stability
C. To monitor contractors’ integrity and performance issues on
federal contracts
D. To track government spending on contracts
Answer: C) To monitor contractors’ integrity and performance
issues on federal contracts
Rationale: FAPIIS is used to track contractors’ integrity and
performance issues, helping agencies make informed decisions
about awarding future contracts based on past behavior.


7. Which of the following is a key function of the "Contracting
Officer’s Technical Representative" (COTR)?
A. To negotiate contract terms and pricing
B. To make unilateral contract modifications
C. To monitor the technical performance of the contract
D. To evaluate proposals and select contractors
Answer: C) To monitor the technical performance of the contract
Rationale: The COTR is responsible for monitoring the
contractor’s technical performance and ensuring that the work
meets contract specifications, though they cannot modify the
contract or handle negotiations.

Document information

Uploaded on
March 10, 2025
Number of pages
33
Written in
2024/2025
Type
Exam (elaborations)
Contains
Questions & answers
$9.99

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Seller avatar
douglasmugwe82
5.0
(1)
Sold
2
Followers
0
Items
4215
Last sold
1 year ago



Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions