SCRUM PSM 1 2025
ANSWER ALL QUESTIONS IN THIS SECTION
QUESTION 1
The Product Owner must release each Increment to production.
a) When it makes sense.
b) To make sure the Development Team is done every Sprint.
c) Whenever the product is free of defects.
d) Without exception. - ANSWERS-a
QUESTION 2
Who creates the definition of "Done"?
a) The Scrum Master as he/she is responsible for the Development Team's
productivity.
b) The Scrum Team, in a collaborative effort where the result is the common
denominator of all members' definition.
c) The Product Owner as he/she is responsible for the product's success.
d) The development organization (or Development Team if none is available from
the development organization). - ANSWERS-d
END OF
PAGE 1
, SCRUM PSM 1 2025
QUESTION 3
Five new Scrum Teams have been created to build one product. A few of the
developers on one of the Development Teams ask the Scrum Master how to
coordinate their work with the order teams. What should the Scrum Master do?
a) Teach the Product Owner to work with the lead developers on ordering Product
Backlog in a way to avoid too much technical and development overlap during a
Sprint.
b) Teach them that it is their responsibility to work with the other teams to create
an integrated increment. - ANSWERS-b
QUESTION 4
Which two things should the Development Team do during the first Sprint?
(choose two)
a) Make up a plan for the rest of the project.
b) Analyze, describe, and document the requirements for the subsequent Sprints.
c) Develop at least one piece of functionality.
d) Analyze, design, and describe the complete architecture and infrastructure.
e) Create an increment of potentially releasable software. - ANSWERS-c,e
END OF
PAGE 2
, SCRUM PSM 1 2025
QUESTION 5
Who determines when it is appropriate to update the Sprint Backlog during a
Sprint?
a) The Project Manager.
b) The Development Team.
c) The Scrum Team.
d) The Product Owner. - ANSWERS-b
QUESTION 6
Who must attend the Daily Scrum?
a) The Scrum Master and Product Owner.
b) The Development Team.
c) The Development Team and Product Owner.
d) The Scrum Team.
e) The Development Team and Scrum Master. - ANSWERS-b
QUESTION 7
When do Development Team members take ownership of a Sprint Backlog item?
END OF
PAGE 3
, SCRUM PSM 1 2025
a) At the Sprint planning meeting.
b) During the Daily Scrum.
c) Never. All Sprint Backlog Items are "owned" by the entire Development Team,
even though each one may be done by an individual Development Team member.
d) Whenever a team member can accommodate more work. - ANSWERS-c
QUESTION 8
The purpose of a Sprint is to produce a done Increment of product.
a) True.
b) False. - ANSWERS-a
QUESTION 9
In the Sprint Planning meeting, the Product Owner and the Development Team
were unable to reach a clear understanding about the highest order Product
Backlog items. Because of this, the Development Team couldn't figure out how
many Product Backlog items it could forecast for the upcoming Sprint. They were
able to agree on a Sprint Goal, however. Which of the following two actions
should the Scrum Master support? (choose two)
a) Cancel the Sprint. Send the entire team to an advanced Scrum traini -
ANSWERS-b,d
END OF
PAGE 4
ANSWER ALL QUESTIONS IN THIS SECTION
QUESTION 1
The Product Owner must release each Increment to production.
a) When it makes sense.
b) To make sure the Development Team is done every Sprint.
c) Whenever the product is free of defects.
d) Without exception. - ANSWERS-a
QUESTION 2
Who creates the definition of "Done"?
a) The Scrum Master as he/she is responsible for the Development Team's
productivity.
b) The Scrum Team, in a collaborative effort where the result is the common
denominator of all members' definition.
c) The Product Owner as he/she is responsible for the product's success.
d) The development organization (or Development Team if none is available from
the development organization). - ANSWERS-d
END OF
PAGE 1
, SCRUM PSM 1 2025
QUESTION 3
Five new Scrum Teams have been created to build one product. A few of the
developers on one of the Development Teams ask the Scrum Master how to
coordinate their work with the order teams. What should the Scrum Master do?
a) Teach the Product Owner to work with the lead developers on ordering Product
Backlog in a way to avoid too much technical and development overlap during a
Sprint.
b) Teach them that it is their responsibility to work with the other teams to create
an integrated increment. - ANSWERS-b
QUESTION 4
Which two things should the Development Team do during the first Sprint?
(choose two)
a) Make up a plan for the rest of the project.
b) Analyze, describe, and document the requirements for the subsequent Sprints.
c) Develop at least one piece of functionality.
d) Analyze, design, and describe the complete architecture and infrastructure.
e) Create an increment of potentially releasable software. - ANSWERS-c,e
END OF
PAGE 2
, SCRUM PSM 1 2025
QUESTION 5
Who determines when it is appropriate to update the Sprint Backlog during a
Sprint?
a) The Project Manager.
b) The Development Team.
c) The Scrum Team.
d) The Product Owner. - ANSWERS-b
QUESTION 6
Who must attend the Daily Scrum?
a) The Scrum Master and Product Owner.
b) The Development Team.
c) The Development Team and Product Owner.
d) The Scrum Team.
e) The Development Team and Scrum Master. - ANSWERS-b
QUESTION 7
When do Development Team members take ownership of a Sprint Backlog item?
END OF
PAGE 3
, SCRUM PSM 1 2025
a) At the Sprint planning meeting.
b) During the Daily Scrum.
c) Never. All Sprint Backlog Items are "owned" by the entire Development Team,
even though each one may be done by an individual Development Team member.
d) Whenever a team member can accommodate more work. - ANSWERS-c
QUESTION 8
The purpose of a Sprint is to produce a done Increment of product.
a) True.
b) False. - ANSWERS-a
QUESTION 9
In the Sprint Planning meeting, the Product Owner and the Development Team
were unable to reach a clear understanding about the highest order Product
Backlog items. Because of this, the Development Team couldn't figure out how
many Product Backlog items it could forecast for the upcoming Sprint. They were
able to agree on a Sprint Goal, however. Which of the following two actions
should the Scrum Master support? (choose two)
a) Cancel the Sprint. Send the entire team to an advanced Scrum traini -
ANSWERS-b,d
END OF
PAGE 4