Dates & Time Lengths - UST Exam Questions
And Answers
Under-dispenser containment was required for all UST systems by
___________.
a.) December 31, 2003
b.) July 1, 1987
c.) January 1, 1984
d.) January 1, 2000 -
correct answer ✅a.) December 31, 2003CCR Title 23, Sec 2636(g)
(C)
According to California Law, UST systems installed after July 1, 2003,
require a one-time ELD test to ensure that the tank is product
tight...
a.) If the tank is located within one (1) mile of a public drinking
water well
b.) If the tank is located within 1000 feet of a public drinking water
well
c.) Unless the tank is equipped with secondary containment
d.) In all cases -
correct answer ✅For ALL tanks before use (H&SC 25290.2 (I))d.) In
all casesH&SC, Sec 25290.2(i)
,Dates & Time Lengths - UST Exam Questions
And Answers
The following is true of secondary containment testing, EXCEPT:
a.) Must be tested every 24 months
b.) Must be tested every 36 months
c.) Results must be submitted to the local agency within 30 days of
testing
d.) Local agency must be notified 48 hours prior to testing -
correct answer ✅a.) Must be tested every 24 months
CCR Title 23, Sec 2637(a)
Records of cathodic protection system maintenance must be kept
on file for ______________.
a.) 10 years
b.) 1.5 years
c.) 3 years
d.) 6.5 years -
correct answer ✅d.) 6.5 years
CCR Title 23, Sec 2712(b)
,Dates & Time Lengths - UST Exam Questions
And Answers
Impressed current cathodic protection systems shall be inspected
no less than every ___________ to ensure that they are in proper
working order:
a.) 60 days
b.) 90 days
c.) 30 days
d.) 120 days -
correct answer ✅a.) 60 days
CCR Title 23, Sec 2635(a)(2)
Monthly monitoring data must be kept on file for
_________________.
a.) 3 years
b.) 6.5 years
c.) 5 years
d.) For the life of the UST system -
correct answer ✅a.) 3 years
CCR Title 23, Sec 2712(b)
, Dates & Time Lengths - UST Exam Questions
And Answers
By December 22, 1998, all automatic line leak detectors installed on
single-walled pressurized piping must be capable of:
a.) Restricting product flow
b.) Triggering an audible and visual alarm
c.) Shutting down the pumping system
d.) Shutting off the flow at the dispenser -
correct answer ✅c.) Shutting down the pumping system
CCR Title 23, Sec 2666(c)
A service technician has performed calibration and maintenance on
an ATG probe; this maintenance record must be kept on file for
______________.
a.) 6.5 years
b.) 3 years
c.) 5 years
d.) Life of the UST system -
correct answer ✅c.) 5 years
CCR Title 23, Sec 2712(b)
And Answers
Under-dispenser containment was required for all UST systems by
___________.
a.) December 31, 2003
b.) July 1, 1987
c.) January 1, 1984
d.) January 1, 2000 -
correct answer ✅a.) December 31, 2003CCR Title 23, Sec 2636(g)
(C)
According to California Law, UST systems installed after July 1, 2003,
require a one-time ELD test to ensure that the tank is product
tight...
a.) If the tank is located within one (1) mile of a public drinking
water well
b.) If the tank is located within 1000 feet of a public drinking water
well
c.) Unless the tank is equipped with secondary containment
d.) In all cases -
correct answer ✅For ALL tanks before use (H&SC 25290.2 (I))d.) In
all casesH&SC, Sec 25290.2(i)
,Dates & Time Lengths - UST Exam Questions
And Answers
The following is true of secondary containment testing, EXCEPT:
a.) Must be tested every 24 months
b.) Must be tested every 36 months
c.) Results must be submitted to the local agency within 30 days of
testing
d.) Local agency must be notified 48 hours prior to testing -
correct answer ✅a.) Must be tested every 24 months
CCR Title 23, Sec 2637(a)
Records of cathodic protection system maintenance must be kept
on file for ______________.
a.) 10 years
b.) 1.5 years
c.) 3 years
d.) 6.5 years -
correct answer ✅d.) 6.5 years
CCR Title 23, Sec 2712(b)
,Dates & Time Lengths - UST Exam Questions
And Answers
Impressed current cathodic protection systems shall be inspected
no less than every ___________ to ensure that they are in proper
working order:
a.) 60 days
b.) 90 days
c.) 30 days
d.) 120 days -
correct answer ✅a.) 60 days
CCR Title 23, Sec 2635(a)(2)
Monthly monitoring data must be kept on file for
_________________.
a.) 3 years
b.) 6.5 years
c.) 5 years
d.) For the life of the UST system -
correct answer ✅a.) 3 years
CCR Title 23, Sec 2712(b)
, Dates & Time Lengths - UST Exam Questions
And Answers
By December 22, 1998, all automatic line leak detectors installed on
single-walled pressurized piping must be capable of:
a.) Restricting product flow
b.) Triggering an audible and visual alarm
c.) Shutting down the pumping system
d.) Shutting off the flow at the dispenser -
correct answer ✅c.) Shutting down the pumping system
CCR Title 23, Sec 2666(c)
A service technician has performed calibration and maintenance on
an ATG probe; this maintenance record must be kept on file for
______________.
a.) 6.5 years
b.) 3 years
c.) 5 years
d.) Life of the UST system -
correct answer ✅c.) 5 years
CCR Title 23, Sec 2712(b)