According to OSHA, while hoisting personnel, the total load must not
exceed what percentage of the crane's rated capacity?"
45%
50%
75%
85%
Give this one a try later!
, d. a.
c. b.
Don't know?
2 of 99
Term
7.When can a crane be side loaded?
a. Dragging a load
b.With a freely suspended load
c. Never
d. Pile-driving
Give this one a try later!
a. c.
d. b.
Don't know?
3 of 99
Term
, 22. Unless the manufacturer states otherwise, what crane
capacity chart is appropriate when a crane is set up with 3 of its 4
outriggers extended and the fourth is retracted?
a.On-outrigger chart
b. On-rubber chart
c. On-outrigger chart minus 20%
d. On-rubber chart plus 20%
Give this one a try later!
b. d.
a. c.
Don't know?
4 of 99
Term
40. How many parts of line are required to hoist a 36,500 lb. load
if the maximum allowable line pull is 9,000 lb.?
a. 3
b. 4
c. 5
d. 6
Give this one a try later!
a. d.
, c. b.
Don't know?
5 of 99
Definition
Critical lift plan, reduction of gross capacity by 25% and one
designated person in charge.
Give this one a try later!
A No special planning is necessary for
single crane lift shall be sufficient
lifts
All personnel can operate without
designation A multi crane lift shall require
Don't know?
6 of 99
Term
The load chart is matched to the crane by:
Give this one a try later!