Question ID: 557
Company Management Is Presented With The Following Information On The Payback
Period For Several Possible Projects. Which Project Is The Best Choice?
A.
Project D With A Payback Period Of 18 Months
B.
Project A With A Payback Period Of 6 Months
C.
Project B With A Payback Period Of 9 Months
D.
Project C With A Payback Period Of 12 Months
Peek At Answer
X
The ACCURATE ANSWERIs B.
The Project With The Shortest Payback Period Is Generally The Best Choice.
Knowledge Area: Integration
Process Group: Initiating
Source: PMP® Exam Prep
Page: 130
,2)
Question ID: 949
All technical work is completed on the project. Which of the following remains to be done?
A.
Validate Scope
B.
Complete Lessons Learned
C.
Plan Risk Responses
D.
Create A Staffing Management Plan
Peek At Answer
X
The ACCURATE ANSWERIs B.
Did You Pick Validate Scope? Then You May Have Forgotten That The Validate Scope Process Is
Done During Project Monitoring And Controlling, Not Project Closing. Planning The Risk Responses
And Creating The Staffing Management Plan Are Done Earlier In The Project. The Lessons Learned
Can Only Be Completed After The Work Is Completed.
Knowledge Area: Integration
Process Group: Closing
Source: PMP® Exam Prep
Page: 164
, 3)
Question ID: 1206
You Are Performing Administrative Closure During The Close Project Or Phase Process.
Outputs Of This Process Include Updated Project Files, Formal Acceptance, And:
A.
Lessons Learned
B.
Statement Of Work Updates
C.
Project Performance Reports
D.
Performance Measurement Documentation
Peek At Answer
X
The ACCURATE ANSWERIs A.
Administrative Closure Is Performed At The End Of Each Phase Of The Project. Outputs Are
Consistent Regardless Of The Phase.
Knowledge Area: Integration
Process Group: Closing
Source: PMP® Exam Prep
Page: 164
Suhail Iqbal
[COMPANY NAME] [Company address]
,1)
Question ID: 557
Company Management Is Presented With The Following Information On The Payback
Period For Several Possible Projects. Which Project Is The Best Choice?
A.
Project D With A Payback Period Of 18 Months
B.
Project A With A Payback Period Of 6 Months
C.
Project B With A Payback Period Of 9 Months
D.
Project C With A Payback Period Of 12 Months
Peek At Answer
X
The ACCURATE ANSWERIs B.
The Project With The Shortest Payback Period Is Generally The Best Choice.
Knowledge Area: Integration
Process Group: Initiating
Source: PMP® Exam Prep
Page: 130
,2)
Question ID: 949
All technical work is completed on the project. Which of the following remains to be done?
A.
Validate Scope
B.
Complete Lessons Learned
C.
Plan Risk Responses
D.
Create A Staffing Management Plan
Peek At Answer
X
The ACCURATE ANSWERIs B.
Did You Pick Validate Scope? Then You May Have Forgotten That The Validate Scope Process Is
Done During Project Monitoring And Controlling, Not Project Closing. Planning The Risk Responses
And Creating The Staffing Management Plan Are Done Earlier In The Project. The Lessons Learned
Can Only Be Completed After The Work Is Completed.
Knowledge Area: Integration
Process Group: Closing
Source: PMP® Exam Prep
Page: 164
, 3)
Question ID: 1206
You Are Performing Administrative Closure During The Close Project Or Phase Process.
Outputs Of This Process Include Updated Project Files, Formal Acceptance, And:
A.
Lessons Learned
B.
Statement Of Work Updates
C.
Project Performance Reports
D.
Performance Measurement Documentation
Peek At Answer
X
The ACCURATE ANSWERIs A.
Administrative Closure Is Performed At The End Of Each Phase Of The Project. Outputs Are
Consistent Regardless Of The Phase.
Knowledge Area: Integration
Process Group: Closing
Source: PMP® Exam Prep
Page: 164