In case of discrepancies among the contract documents, which document takes the
highest precedence? - Correct Answer-Special Provisions
Contractors Recieve progress payments on the basis of? - Correct Answer-Monthly
Progress Estimates
Which of the following sets forth the Department's methods and procedures for
preparing and checking final estimates? - Correct Answer-Preparation and
Documentation Manual (PDM)
Which Document contains a series of Specially designed forms that show both original
estimates of quantities and the final quantities as measured ad accepted? - Correct
Answer-Computation Books
Where are major changes during construction documented and "as-built" conditions
shown? - Correct Answer-Field Notebooks
What identification is needed to show on the front cover of a field book? - Correct
Answer-FEID, Contract number, General contents of the book
When making corrections to a field book entry, you should: - Correct Answer-strike
through, initial and enter correct data and date
What two types of Estimates are needed to pay for the work performed by contractors?
- Correct Answer-Final & Progress Monthly
Which Document contains alignment notes, cross-section notes, linear and area
measurements and dimension sketches? - Correct Answer-Field Notebooks
What should be started on the first lined page (page 1) of a field book? - Correct
Answer-INDEX
An entire page of a field notebook you are using is incorrect, what do you do to correct
the situation? - Correct Answer-Mark the page VOID and reference it to a new page
showing the correct information.
"Check Levels" must be run at the start of a construction project to assure that: - Correct
Answer-Construction will be done to design elevations & final measurements for
payment will be from the same base elevations as the original survey.