Failure to maintain OSHA logs could result in a base penalty of ? - (answers)$1000
The minimum number of employees that will require a contractor to obtain workmen's
compensation insurance is ? - (answers)1 employee
The type of bond that guarantees that the contractor is I'll perform the work in accordance with
the contract is know as a ? bond - (answers)Performance Bond
Short term project schedule is detailed explanation of the next two weeks of construction
activities and should be developed and or reviewed by all the following except ? -
(answers)Architect
The ? usually prepares the project schedule - (answers)Project manager
In order to provide adequate control the project schedule should be formally reviewed and
updated - (answers)At least once every 30 days
你是想要一篇“眼睛容易
A contract will not be enforced if it 阅读的”中文文章
is ? - (answers)Illegal
According to the statute of frauds a contract need not be in writing and still be enforceable in
Florida if it is ? - (answers)Less than $500 in value and less than 1 year in length
The ? has the duty to record and post a Notice of Commencement to improve real property -
(answers)Owner
, A subcontractor started work on his contract with the General Contractor on August 1 1999 The
owner made the final payment to the general contractor on September 13 1999 The latest date the
subcontractor can serve a notice to preserve his claim under the Conatitution Lein Law is what
date and when ? - (answers)September 13 1999 or day before payment
The type of contract we are in the contractor agrees to carry out stipulated job in exchange for a
fix some of the money is a? Contract - (answers)Lump sum
When a contractor has to perform extra work for a subcontractor he will recover the cost in the
form of a? - (answers)Back charge
The ? Should be jointly prepared with the material and equipment schedule - (answers)Project
schedule
Based on the completed contract method for a job bid at $300,000 and currently 66.67%
complete with a gross profit of 16.67% ($50,000) the current amount of profit recognized would
be ? - (answers)$0
Prior to the beginning a drug test program an employer shall ensure that at least ? days elapse
between the notice and the start of testing - (answers)60 days
A lien that is properly perfected may be discharged by Amy of the filling except ? - (answers)The
completion of the project
你是想要一篇“眼睛容易
阅读的”中文文章
After relocating his business to a new location the contractor has _____ days to notify the Board
of his new address - (answers)45 days
______ days is the maximum time after commencing construction for the contractor to give
notice to the owner of his lien rights - (answers)45 days
And action for the breach of a written contract must be brought within ______ years - (answers)5
years
EXAM COMPLETE 100 QUESTIONS AND CORRECT DETAILED
ANSWERS (VERIFIED ANSWERS) |ALREADY GRADED A+
Failure to maintain OSHA logs could result in a base penalty of ? - (answers)$1000
The minimum number of employees that will require a contractor to obtain workmen's
compensation insurance is ? - (answers)1 employee
The type of bond that guarantees that the contractor is I'll perform the work in accordance with
the contract is know as a ? bond - (answers)Performance Bond
Short term project schedule is detailed explanation of the next two weeks of construction
activities and should be developed and or reviewed by all the following except ? -
(answers)Architect
The ? usually prepares the project schedule - (answers)Project manager
In order to provide adequate control the project schedule should be formally reviewed and
updated - (answers)At least once every 30 days
你是想要一篇“眼睛容易
A contract will not be enforced if it 阅读的”中文文章
is ? - (answers)Illegal
According to the statute of frauds a contract need not be in writing and still be enforceable in
Florida if it is ? - (answers)Less than $500 in value and less than 1 year in length
The ? has the duty to record and post a Notice of Commencement to improve real property -
(answers)Owner
, A subcontractor started work on his contract with the General Contractor on August 1 1999 The
owner made the final payment to the general contractor on September 13 1999 The latest date the
subcontractor can serve a notice to preserve his claim under the Conatitution Lein Law is what
date and when ? - (answers)September 13 1999 or day before payment
The type of contract we are in the contractor agrees to carry out stipulated job in exchange for a
fix some of the money is a? Contract - (answers)Lump sum
When a contractor has to perform extra work for a subcontractor he will recover the cost in the
form of a? - (answers)Back charge
The ? Should be jointly prepared with the material and equipment schedule - (answers)Project
schedule
Based on the completed contract method for a job bid at $300,000 and currently 66.67%
complete with a gross profit of 16.67% ($50,000) the current amount of profit recognized would
be ? - (answers)$0
Prior to the beginning a drug test program an employer shall ensure that at least ? days elapse
between the notice and the start of testing - (answers)60 days
A lien that is properly perfected may be discharged by Amy of the filling except ? - (answers)The
completion of the project
你是想要一篇“眼睛容易
阅读的”中文文章
After relocating his business to a new location the contractor has _____ days to notify the Board
of his new address - (answers)45 days
______ days is the maximum time after commencing construction for the contractor to give
notice to the owner of his lien rights - (answers)45 days
And action for the breach of a written contract must be brought within ______ years - (answers)5
years