TCM 226 Exam1 Questions and Correct
Answers
Contractor - Answer-Which of the folowing parties to the construction process is typically responsibke
for scheduling and paying for necessary inspections
Buyout - Answer-The process of awarding subcontractors and procuring materials being furnished by
the GC is called:
True - Answer-The Owner and/or the A/E may request to inspect materials delivered off-site.
Large material deliveries - Answer-Assume that you are the superintendent for a 4,500 sqaure foot
custom home being built in springfield, MO. The site plan and building footprint are shown in the figure
below. Which of the following will be a major concern when developing the job site layout plan?
True - Answer-After RFI response is recieved, the general contractor and its subcontractors should
review the change to see if there is a change in scope of work and possible cost or schedule impacts.
False - Answer-Only the A/E, not the Owner, has the authority to accept non-conforming work.
A dated record of when a document was sent to another party - Answer-A letter of transmittal is:
All of the above are part of the temporary facilities - Answer-Temporary facilities that need to be
considered when planning a jobsite layout include:
Answers
Contractor - Answer-Which of the folowing parties to the construction process is typically responsibke
for scheduling and paying for necessary inspections
Buyout - Answer-The process of awarding subcontractors and procuring materials being furnished by
the GC is called:
True - Answer-The Owner and/or the A/E may request to inspect materials delivered off-site.
Large material deliveries - Answer-Assume that you are the superintendent for a 4,500 sqaure foot
custom home being built in springfield, MO. The site plan and building footprint are shown in the figure
below. Which of the following will be a major concern when developing the job site layout plan?
True - Answer-After RFI response is recieved, the general contractor and its subcontractors should
review the change to see if there is a change in scope of work and possible cost or schedule impacts.
False - Answer-Only the A/E, not the Owner, has the authority to accept non-conforming work.
A dated record of when a document was sent to another party - Answer-A letter of transmittal is:
All of the above are part of the temporary facilities - Answer-Temporary facilities that need to be
considered when planning a jobsite layout include: