Questions correctly solved
The nervous system of lean production - answer Hoshin kanri
Levels of kaizen leadership - answer 1. Tell
2. Show
3. Do it with team member
4. Let team member do, sour learning by asking questions
Morning market - answer Showcase defects created in the last 24 hours and create
countermeasures
Lean improvement process - answer 1. Stabilize the 4Ms
2. Flow
3. Pull
4. Improve the system
Heijunka - answer Load leveling
Lead time - answer Time between customer placing and receiving order
Kosu - answer Worker hours
Kaizen blitz - answer Small but rapid changes
Kaikaku - answer Radical change
JIT - answer Just in time: producing the right part in the right quantity at the right
time.
Involvement goals - answer Explicit goal is PQCDSM.
Deeper goal is improve team member capability.
PQCDSM - answer Productivity
Quality
Cost
Delivery
Safety
Morale
Jidoka - answer Stop production so production never has to stop