Develop Schedule Process - The process of analyzing activity sequences, durations, resource requirements, and schedule constraints to create the project schedule model. Develop Schedule Process - The following tools and techniques are part of this process: •Schedule network analysis •CPM •CCM •Resource optimization techniques •Modeling techniques •Lead and lags •Schedule compression •Scheduling tool Planned Dates - Key benefit of the Develop Schedule process is that it generates ____ ____ for completing project activities.

Show more Read less
Institution
MBA 742
Course
MBA 742









Whoops! We can’t load your doc right now. Try again or contact support.

Written for

Institution
MBA 742
Course
MBA 742

Document information

Uploaded on
February 6, 2025
Number of pages
13
Written in
2024/2025
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

Content preview

MBA 742 - MODULE 3 QUESTIONS AND
ANSWERS
Develop Schedule Process - ✔✔The process of analyzing activity sequences,
durations, resource requirements, and schedule constraints to create the project
schedule model.

Develop Schedule Process - ✔✔The following tools and techniques are part of this
process:
•Schedule network analysis
•CPM
•CCM
•Resource optimization techniques
•Modeling techniques
•Lead and lags
•Schedule compression
•Scheduling tool

Planned Dates - ✔✔Key benefit of the Develop Schedule process is that it generates
____ ____ for completing project activities.

Schedule Network Analysis - ✔✔The techniques of identifying early and late start dates,
as well as early and late finish dates, for the uncompleted portions of project schedule
activities.

Critical Path - ✔✔the sequence of activities the represents the longest path through the
project, which determines the shortest possible duration

CPM (Critical Path Method) - ✔✔A method used to estimate the minimum project
duration and determine the amount of scheduling flexibility on the logical network paths
within the schedule module.

CCM (Critical Chain Method) - ✔✔A schedule method that allows the project team to
place buffers on any project schedule path to account for limited resources and project
uncertainties.

tasks & resources - ✔✔CPM is focused on ____ and CCM focuses on the ____.

task - ✔✔CPM is a ____ based model

Resource - ✔✔CCM is a ____ based model

, Forward & Backward - ✔✔In order to determine the project's critical path, it is necessary
to perform both a ____ and ____ pass through the network.

Forward - ✔✔In CPM, a ____ pass will ID the early-start and early finish times.

Backward - ✔✔In CPM, a ____ pass will ID the late-start and late-finish times.

Forward Pass - ✔✔A critical path method technique for calculating the early start and
early finish dates by working forward through the schedule model from the project start
date or a given point in time.

Backward Pass - ✔✔A critical path method technique for calculating the late start and
late finish dates by working backward through the schedule model from the project end
date.

Early Start (ES) - ✔✔In CPM, the earliest date the activity can start.

Early Finish (EF) - ✔✔In CPM, the earliest date the activity can finish

Late Finish (LF) - ✔✔In CPM, the latest date that the activity can finish without causing
a delay to the project completion date.

Late Start (LS) - ✔✔In CPM, the latest date that the activity can start without causing a
delay to the project completion date.

Free Float - ✔✔The amount of time that a schedule activity can be delayed without
delaying the early start date of any successor or violating a schedule constraint.

Total Float - ✔✔The amount of time that a schedule activity can be delayed or extended
from its early start date without delaying the project finish date or violating a schedule
constraint.

Critical - ✔✔A useful way of describing the critical path is as a continuous string(s) of
____ activities in the schedule between the start and finish of the project.

Duration - ✔✔The sum of the activity durations in the critical path is equal to the
project's ____; therefore a delay to any critical activity will result in a delay to the project
completion date.

Critical Activity - ✔✔An activity that is on the project's critical path. Does not possess
any float, total float = 0.
$11.99
Get access to the full document:

100% satisfaction guarantee
Immediately available after payment
Both online and in PDF
No strings attached

Get to know the seller
Seller avatar
ammon

Get to know the seller

Seller avatar
ammon Glendale Community College
View profile
Follow You need to be logged in order to follow users or courses
Sold
0
Member since
1 year
Number of followers
0
Documents
42
Last sold
-

0.0

0 reviews

5
0
4
0
3
0
2
0
1
0

Recently viewed by you

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Frequently asked questions