POWER SYSTEM ANALYSIS AND DESIGN 1 CHAPTER 3 QUESTIONS AND ANSWERS System developers can initiate a formal project as early as the preliminary investigation stage, or later on, as analysis, design, and implementation activities occur. - CORRECT ANSWERTrue

Content preview

POWER SYSTEM ANALYSIS AND DESIGN 1 CHAPTER 3
QUESTIONS AND ANSWERS
System developers can initiate a formal project as early as the preliminary investigation stage, or
later on, as analysis, design, and implementation activities occur. - CORRECT
ANSWER✅✅✅True


Program Evaluation Review Technique (PERT)/Critical Path Method (CPM) and Gantt charts
are mutually exclusive techniques. - CORRECT ANSWER✅✅✅False


Using a work breakdown structure (WBS) allows one to manage a project as one large task. -
CORRECT ANSWER✅✅✅False


In most systems analysis tasks, time and people are interchangeable. - CORRECT
ANSWER✅✅✅False


The prior experience method to make time and cost estimates works best for large projects. -
CORRECT ANSWER✅✅✅False


In a Program Evaluation Review Technique (PERT)/Critical Path Method (CPM) chart, each
rectangular box, called a task box, has five sections that contain important information about a
task. - CORRECT ANSWER✅✅✅True


When tasks must be completed one after another, they are called concurrent tasks. - CORRECT
ANSWER✅✅✅False


If any task along a critical path falls behind schedule, the entire project will be delayed. -
CORRECT ANSWER✅✅✅True


Generally, systems analysts review the work of other systems analysts, and programmers review
the work of other programmers, as a form of peer review, in structured walk-throughs. -
CORRECT ANSWER✅✅✅True

, If team members lack experience with certain aspects of the required technology, temporary help
might be obtained from IT consultants or part-time staff. - CORRECT ANSWER✅✅✅True


Quantitative risk analysis evaluates each risk by estimating the probability that it will occur and
the degree of impact. - CORRECT ANSWER✅✅✅False


Critical time is the amount of time that the task could be late without pushing back the
completion date of the entire project. - CORRECT ANSWER✅✅✅False


The purpose of quantitative risk analysis is to understand the actual impact in terms of dollars,
time, project scope, or quality. - CORRECT ANSWER✅✅✅True


The three legs of the project triangle are management, staff, and clients. - CORRECT
ANSWER✅✅✅False


Scheduling involves selecting and staffing the project team and assigning specific tasks to team
members. - CORRECT ANSWER✅✅✅True


Henry L. Gantt developed Gantt charts almost 100 years ago. - CORRECT
ANSWER✅✅✅True


In addition to tasks, every project has events, or milestones. - CORRECT
ANSWER✅✅✅True


Weight is an importance value that is added to each duration estimate. - CORRECT
ANSWER✅✅✅True


A project manager should never develop time and cost estimates based on the resources used for
previously developed information systems. - CORRECT ANSWER✅✅✅False

Document information

Uploaded on
February 6, 2025
Number of pages
8
Written in
2024/2025
Type
Exam (elaborations)
Contains
Questions & answers
$9.49

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
STANGRADES
3.3
(15)
Sold
99
Followers
2
Items
11990
Last sold
5 hours ago



Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions