CDT COMPREHENSIVE EXAM LATEST EXAM 2025
| ALL 170 QUESTIONS AND CORRECT ANSWERS |
ALREADY GRADED A+ | NEWEST EXAM (JUST
RELEASED)
Save
Terms in this set (100)
1. The method of b) Conditions of the Contract.
computation of
Contractor's overhead
and profits for Change
Order prices, where both
additions and deletions
are involved, is found in
the:
a) Agreement.
b) Conditions of the
Contract.
c) Division 01.
d) Instructions to Bidders.
2. General Requirements c) Specifications.
are part of:
a) Supplementary
Conditions.
b) Bidding Requirements.
c) Specifications.
d) Summary of Work.
https://quizlet.com/1001232090/cdt-comprehensive-exam-latest-exam-2025-all-170-questions-and-correct-answers-already-graded-a-newest-exam-j… 1/41
,2/4/25, 1:19 PM CDT COMPREHENSIVE EXAM LATEST EXAM 2025 | ALL 170 QUESTIONS AND CORRECT ANSWERS | ALREADY GRADED A+…
3. The three essential a) Requirements, Criteria, and Tests.
considerations in the
evaluation of a product
are:
a) Requirements, Criteria,
and Tests.
b) Costs, Maintenance,
and Installation.
c) Life Cycle Cost,
Installation Cost, and
Maintenance Cost.
d) Case studies, Failures,
and Problems.
4. Whose responsibility is b) The Contractor
it to furnish the Shop
Drawings?
a) The Architect/Engineer
b) The Contractor
c) The Owner
d) The Subcontractor
5. The division of the Work c) Division 01.
among multiple prime
Contracts is described in:
a) Instructions to Bidders.
b) Supplementary
Conditions.
c) Division 01.
d) Special Conditions.
https://quizlet.com/1001232090/cdt-comprehensive-exam-latest-exam-2025-all-170-questions-and-correct-answers-already-graded-a-newest-exam-j… 2/41
,2/4/25, 1:19 PM CDT COMPREHENSIVE EXAM LATEST EXAM 2025 | ALL 170 QUESTIONS AND CORRECT ANSWERS | ALREADY GRADED A+…
6. During the Project d) Assist in financial feasibility studies
Conception Stage, the
A/E may be retained to:
a) Develop outline
specifications
b) Describe the character
of the mechanical system
c) Prepare renderings
d) Assist in financial
feasibility studies
7. What is the main c) to organize the Project Manual, reference keynotes
purpose of and detailed cost estimates.
MasterFormat?
a) for scheduling, value
management, recording of
design data and managing
costs.
b) used during the
planning stage of a
project.
c) to organize the Project
Manual, reference
keynotes and detailed
cost estimates.
d) when there is a
standardized need for
information to appear
upon each page of a
project manual.
https://quizlet.com/1001232090/cdt-comprehensive-exam-latest-exam-2025-all-170-questions-and-correct-answers-already-graded-a-newest-exam-j… 3/41
, 2/4/25, 1:19 PM CDT COMPREHENSIVE EXAM LATEST EXAM 2025 | ALL 170 QUESTIONS AND CORRECT ANSWERS | ALREADY GRADED A+…
8. The person who c) Guarantor
becomes secondarily
liable for another's debt or
performance is called the:
a) Guarantee
b) Warrantor
c) Guarantor
d) Warrantee
9. Integrated projects are d) "Just as needed" team involvement to reduce
distinguished by all of the owner's pre-construction expenses
following characteristics
except:
a) Development of virtual
project model through
input from a collaborative
team
b) Trust-based
collaboration between
project team members
c) Maximized efficiency
through design,
fabrication, and
construction
d) "Just as needed" team
involvement to reduce
owner's pre-construction
expenses