True or False: In most instances, the EPCM model is structured based on a cost-reimbursable fee structure or a unit rate fee structure. Ans-True Which stage in AWP is when you turn over the project and do project closeout? Ans-Stage 5 All change orders must be approved by who/whom? Ans-The owner and contractor, both must agree In construction, a change order refers to the documentation of an agreement to do what following tasks, select all that apply Ans-deviate from the original scope; add work; subtract work; alter the design True or False: Proper change order management enables teams to mitigate significant costs and schedule disruptions in construction. Ans-True The procurement plan must be aligned with your what two areas. Select the two that are correct. Ans-engineering design basis and construction strategy

Content preview

CM 4211 - Final Exam (modules 5-7)
questions with verified answers
True or False: In most instances, the EPCM model is structured based on a cost-
reimbursable fee structure or a unit rate fee structure. Ans✓✓-True


Which stage in AWP is when you turn over the project and do project closeout?
Ans✓✓-Stage 5


All change orders must be approved by who/whom? Ans✓✓-The owner and
contractor, both must agree


In construction, a change order refers to the documentation of an agreement to
do what following tasks, select all that apply Ans✓✓-deviate from the original
scope; add work; subtract work; alter the design


True or False: Proper change order management enables teams to mitigate
significant costs and schedule disruptions in construction. Ans✓✓-True


The procurement plan must be aligned with your what two areas. Select the two
that are correct. Ans✓✓-engineering design basis and construction strategy


EPCM contractor is responsible for establishing contractual agreements on behalf
of the owner or principal with other parties, select all that apply Ans✓✓-vendors;
sub-contractors; other contractors; vendors of sub-contractors

, For large-scale, critical infrastructure projects, an EPC contract provides a highly
effective _____________. Ans✓✓-turnkey solution


True or False: EPCM stands for engineering, procurement, and construction
management. Ans✓✓-true


True or False: At its core, change order is work that is added or removed from the
original contractor's scope of work, as agreed upon in the contract signed by the
client and contractor before work began. Ans✓✓-true


True or False: Advanced work packaging is an industry best practice
(methodology) that focuses on proper & thorough front-end planning, along with
the alignment of EPCM activities and deliverables, to achieve improved project
performance. Ans✓✓-true


EPC contracts are an all-encompassing what type of contract? Ans✓✓-lump sum


True or False: The document control system in the AWP method will have your
schedule, purchase orders, and requisitions. Ans✓✓-true


All change orders need to include detailed information, including __________.
Select all that apply Ans✓✓-a summary by the contractor of the total cost of the
proposed change; a description of the requested change compared to the original
contract or bid; itemized documentation of any subcontractor costs; a statement
of the contractual basis for the requested change and its impact on the project
completion date


True or False: The journal of construction engineering explains, " various reasons
for construction cost and schedule overruns in any project include design error,

Document information

Uploaded on
January 29, 2025
Number of pages
8
Written in
2024/2025
Type
Exam (elaborations)
Contains
Questions & answers
$14.99

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
cracker
3.8
(401)
Sold
2172
Followers
1346
Items
50102
Last sold
6 hours ago



Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions