In a Factory/Industrial (F1) ZONE, division 2, the minimum lot width is __________
the minimum lot depth is __________ feet respectively.
A. 50, 75
B. 75, 100
C. 100, 125
D. 125, 200 - ANSWER✅✅B. 75, 100
No sign other than an official traffic sign shall be erected within __________ feet of
the lines of any street.
A. 2
B. 4
C. 5
D. 8 - ANSWER✅✅A. 2
For any use contrary to any building or parcel of land regulated by the International
Zoning Code, the Code Official shall be permitted to serve notice on:
A. any person causing such use to be continued.
B. the property owner, alone.
C. the business owner, alone.
, D. the property management group. - ANSWER✅✅A. any person causing such use
to be continued.
The occupancy of a carport and a drugstore shall be classified as __________ and
__________ respectively.
A. Group U, Group M
B. Group M, Group U
C. Group R, Group M
D. Group R, Group B - ANSWER✅✅A. Group U, Group M
A site plan recently submitted identifies an occupancy that is not directly mentioned
in the code, but is most closely related to a professional, service-type transaction use.
Therefore, it would be classified as a____occupancy.
A. storage
B. business
C. mercantile
D. institutional - ANSWER✅✅B. business
A conditional permit shall be revoked when the applicant fails to comply with
conditions imposed by the ____
A. Building Official
B. Zoning Inspector
C. Planning Commission
D. Hearing Examiner - ANSWER✅✅D. Hearing Examiner
Which of the following uses may be issued a certificate of occupancy as a Use Group
I-2?
A. Hospital
B. Assisted living facility
C. Social rehabilitation facility
D. Correctional center - ANSWER✅✅A. Hospital
A contractor submits HVAC plans for a new commercial bldg before the foundation
plans have been submitted. Can a HVAC permit be issued prior to the submittal of
foundation plans?
A. No.
B. Yes, as a phased approval.
C. Only for structures less than 3 stories in height.
D. Yes, except for structures greater than 3 stories in height. - ANSWER✅✅B. Yes, as
a phased approval.