Term
What is EHV?
Give this one a try later!
When the resource performance
By 1415 the day prior to operation
falls below 40%
, Extra high voltage. Classified It will be place in "Pending
as 345kv and above Evaluation" status
Don't know?
2 of 65
Term
What frequency would PJM set to correct for fast-time error?
Give this one a try later!
60.00hz 59.98Hz
59.50hz 60.05hz
Don't know?
3 of 65
Term
During low voltage situations, caps should be ___ and shunt reactors should
be ___
Give this one a try later!
, caps should be monitored; shunt caps should be reduced; shunt
reactors should be adjusted. reactors should be maintained.
caps should be put into
service; shunt reactors should self-scheduling. the unit must be
be taken out of service. committed.
Don't know?
4 of 65
Term
When is the DA market rebid period?
Give this one a try later!
1330-1415 1500-1600
1000-1100 1200-1300
Don't know?
5 of 65
Term
What time period is the re-bid period?
, Give this one a try later!
1400-1500 1500-1600
1330-1415 1200-1300
Don't know?
6 of 65
Term
Control center facilities must have a minimum of how many days
of fuel for the backup generator?
Give this one a try later!
5 days 1 day
10 days 3 days
Don't know?