Mary Ann is a project manager who is managing the construction of a new house.
What is the earliest phase of the project in which Mary Ann would assign jobs to the
construction contractors?
Phase 2
Which of the following describes a program?
Several projects that address the same opportunity
Which of the following characteristics did project manager Angela demonstrate when
she scheduled several meetings during the planning of a project, notified each team
member, and sent reminders prior to meeting times?
Organizational Skills
Project manager Caedan estimated the number of days it would take to paint lines and
erect bleachers in the open space of his town's park to create soccer fields for a new
youth soccer league. Which of the estimate types below did Caedan make?
Time
What is the first step a project manager will take when defining the project scope?
Identify stakeholders
Which component of SMART is missing from the goal "Lisa will host a graduation party
immediately following the graduation ceremony?"
Measurable
Which of the following is NOT true regarding the role of a project manager?
A project manager must have expertise relevant to the assigned project.
Which of the following is true regarding project methodologies?
The phase-based project methodology goes through phases sequentially.
Which of the following is an example of a change in scope for a project?
Features of a deliverable are changed
Elizabeth is planning a high school reunion at the city park. When researching the
weather, she found that there was a 15% chance that it would rain on the selected
weekend. However, if it did rain, it would be a disaster -- they would have to rent a tent
to cover the seating area, they wouldn't have any indoor space for the caterer, and their
DJ wouldn't be able to perform. Which of the following lists the corresponding degree of
probability and the level of impact that a rainy weekend would have?
, Low probability and high negative impact
Which of the following is included in a business case for a project?
Benefits
Which of the following responsibilities is performed by a project manager?
Manages a set of deliverables, budget, and team members
What is the first step a project manager performs after officially beginning a project?
Create a scope document
Which of the following is the least likely reason for failure of Stacey's construction
project if several stakeholders involved in the project were unable to agree on the final
design of the deliverables?
Problems with unforeseeable circumstances
Which of the following is an example of a process project?
Change the methods for hiring teachers
Which of the following is a checkpoint where some aspect of the project work is
approved in order to proceed?
Gate
Which of the following should a project manager do to prepare for the scope approval
process?
Determine the approvals that are required for sponsors to sign-off on.
Which of the following is an expectation that relates to the overall impact the project
deliverables will have once the project is implemented?
Project benefit expectation
Elena is working on a project to create a new pet leash for her pet supply company.
Which of the following items is a deliverable, as opposed to a requirement?
Prototypes to showcase at stakeholder meetings
Which of the following stakeholders are assigned specific tasks needed to meet
deliverables?
Project team members
Which of the following scope elements answers a "What" question in developing the
scope document?
Documenting stakeholder expectations
Which of the following correctly describes probability?
It involves the likelihood a risk will occur for a project.