T/F: Under the CQC inspection process used by some federal agencies, the
Contractor is responsible to provide for the organization and maintenance of
an inspection system. - ANSWER True
T/F: A multiple-prime project requires the owner to coordinate the various
trade contractors with which it has contracted. - ANSWER True
T/F: Legal barriers may be encountered when attempting to implement the
design-build process in the public sector. - ANSWER True
Chronological order of the 5 steps of initiating a construction project. -
ANSWER Advertise for bids
Open bids
Award contract
Sign the contract
Issue notice to proceed
T/F: In fast-track projects with multiple contractors, the services of a
professional construction management firm (Agency CM) are essential. -
ANSWER True
, Which phases can a professional construction management firm (agency CM)
participate in? - ANSWER Conception
Program Planning
Design
Construction
Closeout
What is the order of routing submittals from subcontractor to designer? -
ANSWER Subcontractor
General Contractor
Resident Project Representative
Project Manager
Design Reviewers
T/F: The Resident Project Representative should not lead the Contractor's
work. - ANSWER True
T/F: If the Resident Project Representative identifies an issue in the
Subcontractor's work, she/he should direct that Subcontractor directly. -
ANSWER False
Complete Solution
T/F: Under the CQC inspection process used by some federal agencies, the
Contractor is responsible to provide for the organization and maintenance of
an inspection system. - ANSWER True
T/F: A multiple-prime project requires the owner to coordinate the various
trade contractors with which it has contracted. - ANSWER True
T/F: Legal barriers may be encountered when attempting to implement the
design-build process in the public sector. - ANSWER True
Chronological order of the 5 steps of initiating a construction project. -
ANSWER Advertise for bids
Open bids
Award contract
Sign the contract
Issue notice to proceed
T/F: In fast-track projects with multiple contractors, the services of a
professional construction management firm (Agency CM) are essential. -
ANSWER True
, Which phases can a professional construction management firm (agency CM)
participate in? - ANSWER Conception
Program Planning
Design
Construction
Closeout
What is the order of routing submittals from subcontractor to designer? -
ANSWER Subcontractor
General Contractor
Resident Project Representative
Project Manager
Design Reviewers
T/F: The Resident Project Representative should not lead the Contractor's
work. - ANSWER True
T/F: If the Resident Project Representative identifies an issue in the
Subcontractor's work, she/he should direct that Subcontractor directly. -
ANSWER False