ASPHALT PAVING LEVEL 1 EXAM
QUESTIONS AND ANSWERS
What size is a whole lot of super pave asphalt?
One thousand tonnes
Between 1,000 and 2000 tonnes
Between 2000 and 4000 tonnes
Production in one day: 2000–4000 tonnes
In fdot mix designs, which is not commonly utilised as an asphalt binder?
PG 52-28 PG 58-22
PG 62-22
PG 76-22 (PMA)
PG 82-22 (PMA) - PG 62-22 ANSWER
The density cores used for verification testing are cut by whom?
The technician for verification
The contractor
The technician for independent verification testing
None of the aforementioned—ANSWER The contractor
Five sublots and four cores make up a whole lot. T/F-ANSWER Untrue
What is most crucial for the asphalt mix's constant compaction?
The temperature of the mixture is higher.
The temperature of the mixture is lower.
The temperature of the mixture is constant.
Compaction is unaffected by the mix's temperature. ANSWER The temperature
of the mixture is constant.
By normal stationing criteria, R1 would be ____ as opposed to R2.
Nearer the centerline
Nearer the outer shoulder
closure of the inner shoulder
, A and C together - ANSWER A and C together
If the rolling straightedge needle enters the red zone while being used,
signifying an unacceptably high spot in the segment, you then - ANSWER Put
a mark on the pavement where the needle enters the red zone, then another mark
where it exits, and so on.
The 15-foot manual straightedge for bridge approach slabs should be positioned
so that ____ is on the bridge deck.
One inch
Half of the straightedge, exactly
The whole straightedge
None of the aforementioned—ANSWER One inch
On a project, set the ___ on the newly laid pavement, overlapping the first
transverse joint by one inch.
15-foot manual straight edge at 4 feet level
Straightedge rolling
Everything mentioned above—ANSWER 15-foot manual straight edge
In order to check the rolling straight edge's low side during calibration:
Shims should be placed beneath the outer wheels.
The rolling straight edge should be placed on a flat surface.
Under each outside wheel, place a 3/16-inch shin; both sides of the gauge
should read zero.
Shims should be placed beneath the centre wheel. ANSWER Under each
outside wheel, place a 3/16-inch shin; both sides of the gauge should read zero.
In order to check the rolling straight edge's high side during calibration:
Shims should be placed beneath the outer wheels.
Shims should be placed beneath the centre wheel.
The rolling straight edge should be placed on a flat surface.
A 3/16-inch shin should be positioned beneath the centre wheel. Both sides of
the gauge should display zero. ANSWER A 3/16-inch shim should be
positioned beneath the centre wheel. Both sides of the gauge should display
zero.
When manually testing the cross slope, what information is necessary?
QUESTIONS AND ANSWERS
What size is a whole lot of super pave asphalt?
One thousand tonnes
Between 1,000 and 2000 tonnes
Between 2000 and 4000 tonnes
Production in one day: 2000–4000 tonnes
In fdot mix designs, which is not commonly utilised as an asphalt binder?
PG 52-28 PG 58-22
PG 62-22
PG 76-22 (PMA)
PG 82-22 (PMA) - PG 62-22 ANSWER
The density cores used for verification testing are cut by whom?
The technician for verification
The contractor
The technician for independent verification testing
None of the aforementioned—ANSWER The contractor
Five sublots and four cores make up a whole lot. T/F-ANSWER Untrue
What is most crucial for the asphalt mix's constant compaction?
The temperature of the mixture is higher.
The temperature of the mixture is lower.
The temperature of the mixture is constant.
Compaction is unaffected by the mix's temperature. ANSWER The temperature
of the mixture is constant.
By normal stationing criteria, R1 would be ____ as opposed to R2.
Nearer the centerline
Nearer the outer shoulder
closure of the inner shoulder
, A and C together - ANSWER A and C together
If the rolling straightedge needle enters the red zone while being used,
signifying an unacceptably high spot in the segment, you then - ANSWER Put
a mark on the pavement where the needle enters the red zone, then another mark
where it exits, and so on.
The 15-foot manual straightedge for bridge approach slabs should be positioned
so that ____ is on the bridge deck.
One inch
Half of the straightedge, exactly
The whole straightedge
None of the aforementioned—ANSWER One inch
On a project, set the ___ on the newly laid pavement, overlapping the first
transverse joint by one inch.
15-foot manual straight edge at 4 feet level
Straightedge rolling
Everything mentioned above—ANSWER 15-foot manual straight edge
In order to check the rolling straight edge's low side during calibration:
Shims should be placed beneath the outer wheels.
The rolling straight edge should be placed on a flat surface.
Under each outside wheel, place a 3/16-inch shin; both sides of the gauge
should read zero.
Shims should be placed beneath the centre wheel. ANSWER Under each
outside wheel, place a 3/16-inch shin; both sides of the gauge should read zero.
In order to check the rolling straight edge's high side during calibration:
Shims should be placed beneath the outer wheels.
Shims should be placed beneath the centre wheel.
The rolling straight edge should be placed on a flat surface.
A 3/16-inch shin should be positioned beneath the centre wheel. Both sides of
the gauge should display zero. ANSWER A 3/16-inch shim should be
positioned beneath the centre wheel. Both sides of the gauge should display
zero.
When manually testing the cross slope, what information is necessary?