The right to repossess or replevy unused materials from a jobsite will not be effective if
someone, in good faith, purchased it after removal from the site of the improvement. -
Answers- True.

The contractor must within _____ days after the receipt of the property owner's request,
furnishish to property owner or the property owner's agent a list of the subcontractors
and suppliers who have a contract with the contractor as of the date the request is
received by the contractor. - Answers- 10 days.

No lien provided by part 713.22 will continue for no longer then _______ years after the
recording of an amended claim of lien that shows a later date of final furnishing of labor,
services, or materials. - Answers- 1 year

The lien of any lienor upon whom Notice of contest of Lien is served and who fails to
institute a suit to enforce his or her lien within ________ days after service of such
notice will be extinguished automatically. - Answers- 60

The payment bond is required to ______ an owner under s. 713.23 must be furnished
by the contractor in at least the amount of the original contract price before commencing
the construction of the improvement under the direct contract. - Answers- exempt

A copy the payment bond must be attached to the Notice of Commencement when it is
_______. - Answers- recorded

Anyone who willfully files a fraudulent lien as defined in 713.31 commits a felony of the
______ degree - Answers- third

When a construction project is "put out" for bid, the contractors are given the plans and
specifications for the project. If any deviations for these specifications occur, who will be
held responsible and may be required to correct them at their own expense? -
Answers- The contractor

The ______ for a protect are interpreted as a legal document that specifically defines
the responsibilities of the owner and his representatives intended for the project and
what the contractors responsibilities are. - Answers- specifications

The CSI-MASTERFORMAT divides the specifications into __________ specific
divisions to provide a standard reference and filing numbers for bidding and contract
forms. - Answers- 50

Which of the following would appear as a heading in the index of the General Clauses
and Conditions sections of General Requirements? - Answers- All of these ( General
Conditions, Notice to Bidders and Proposal)

, _________ is the contractors price for performing the work as specified. - Answers-
The proposal

"Contract Documents" "Insurance," "payments," and "Guarantee" are some typical items
that would be included under what heading in the General Clauses and Conditions
section? - Answers- General Conditions

The square footage method of estimating is always recommended for lump-sum
contracts. - Answers- False

The typical _______ provides the necessary control devices for the accumulation of
estimates into the final bid. - Answers- Estimate summary sheet

A property perfected lien may be discharged by an order of the circuit court of the _____
where the property is located. - Answers- county

When any interested party files a complaint, the clerk will issue a summons to the lienor
to show cause within _____ days why his or her lien should not to be enforced by action
or vacated and canceled of record. - Answers- 20 days

If a lienor fails to show cause why his or her lien should not be enforced or fails to start
such action before the return date of the summons, the court will immediately order
cancellation of the lien. - Answers- True

No lien provided by part 713.22 will continue for longer then ____ years after the claim
of lien has been recorded. - Answers- 1 year

What type of estimate is an accurate estimating method that consists of listing all
material and labor needed for an element of work or project - Answers- Detailed Survey

_________ estimates are used as a check to determine if sufficient materials are
available to construct or complete a project. - Answers- Material

Which of the following are types of labor estimates?
I. Preliminary manpower estimates
II. Detailed manpower estimates
III.Production manpower estimates - Answers- I and II only

The satisfactory completion of the work for the stand number of dollars in a lump-sum
contract remains the obligation of the contractor regardless of the troubles that may be
experienced in the course of construction activities. - Answers- True

The summary account can be updated on a ________ basis. - Answers- All of these (
monthly, weekly, daily)

Document information

Uploaded on
January 9, 2025
Number of pages
7
Written in
2024/2025
Type
Exam (elaborations)
Contains
Questions & answers
$11.49

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
GEEKA
3.8
(367)
Sold
2183
Followers
1449
Items
61377
Last sold
1 day ago



Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions