Which of the following is true about Scrum? Select two.
A. Burndown and Burnup chart help teams track the progress of the current sprint.
B. It is encouraged to make iteration scope changes during the sprint
C. In Sprint Retrospective, we talk about what we build, give a demo and get
customer/client feedback
D. In daily stand-up, everybody talks about what they worked, what they are planning to
work on and share any impediments they have.
E. In Sprint Review, we talk about process and talk about what was working, what didn't
work and how we can improve. - ANSWER - A D
Which of the following is true about product and sprint backlogs? Select two.
A. A sprint backlog is created during the sprint planning meeting.
B. The product backlog is a prioritized backlog with highest priority items on the top.
C. Sprint and product backlogs are same thing.
D. A sprint backlog has all of the items contained in the product backlog. - ANSWER - A
B
What are some of the challenges with the Waterfall methods that prompted the software
industry to come up with alternatives like Agile? (select 2)
A. Projects cost too much.
B. It is difficult to predict user/customer needs.
C. Projects were very complex and big.
D. Incorrect interpretations of requirements by developers go undetected for a long
time. During user acceptance tests, these issues are discovered but it is very late. -
ANSWER - B D
Which of the following statements aligns with the value "Working software over
comprehensive documentation" of Agile manifesto? (select any 2)
A. A manager tells the team: "Writing certain documentation is company policy so we
must create them irrespective of its use.
B. An Agile coach says to the team "Documentation is of no use."
C. Value delivering software over writing documentation.
D. If documentation is absolutely essential then create it. - ANSWER - C D
Which one of the following statements/situations/conversations align with an Agile
mindset?
, A. Manager: "The customer is suggesting another change in feature X which is
complete as per specification. They agree that it was built as we agreed upon but it
lacks some functionality and will result in user frustration. Should we implement the
change or not?"
Developer: "Yes, if it does not fulfill user needs, we should make the change."
B. A manager providing a status update to a customer says: "We are done with
requirements and design so we are 50% done."
C. A software vendor says to a client: "We must define exactly what the user needs and
put that in agreement."
D. A manager e-mails her team: "Meeting face to face just for a 15 minute discussion is
inefficient, let us all just dial-in from our desk." - ANSWER - A
Which of the following is TRUE about lean startup? (select all that apply)
A. The concept of "Validated Learning" in Lean Startup means validating your learning
and new ideas with your manager before you implement.
B. Lean Startup concept is primarily applicable to startup companies. It is not applicable
for bigger organizations.
C. Lean Startup concepts recommends to go through Build-Measure-Learn cycles as
fast as you can.
D. In Lean Startup, you try to validate/invalidate your assumptions (crucial for the
success of your product) as fast as you can. - ANSWER - C D
Which of following is valid on a Kanban Board? (select any 2)
A. WIP limit for Step X is 3. Step X is divided into "Doing" and "Done." Number of items
in "Doing" column is 4, and number of items in "Done" column is 0
B. WIP limit for Step X is 3. Step X is divided into "Doing" and "Done." Number of items
in "Doing" column is 2, and number of items in "Done" column is 1
C. WIP limit for Step X is 3. Step X is divided into "Doing" and "Done." Number of items
in "Doing" column is 3, and number of items in "Done" column is 2
D. WIP limit for Step X is 3. Step X is divided into "Doing" and "Done." Number of items
in "Doing" column is 2, and number of items in "Done" column is 1. One of the items in
the previous step is done and developer wants to move that item to Step X
E. WIP limit for Step X is 5. Step X is divided into "Doing" and "Done." Number of items
in "Doing" column is 3, and number of items in "Done" column is - ANSWER - B E
Which of the following Framework/process model supports Agile Mindset? (select all
that apply)
A. Lean Startup
B. Waterfall
C. V-Model
D. Scrum
E. Crystal