ANSWERS 100% CORRECT
What are some of the challenges with the Waterfall methods that prompted the software
industry to come up with alternatives like Agile? (select 2)
A. It is difficult to predict user/customer needs.
B. Incorrect interpretations of requirements by developers go undetected for a long time.
During user acceptance tests, these issues are discovered but it is very late.
C. Projects were very complex and big.
D. Projects cost too much. - ANSWER - AB
Which of following is valid on a Kanban Board? (select any 2)
A. WIP limit for Step X is 5. Step X is divided into "Doing" and "Done." Number of items
in "Doing" column is 3, and number of items in "Done" column is 1. One of the item in
previous step is done and developer wants to move that item to Step X
B. WIP limit for Step X is 3. Step X is divided into "Doing" and "Done." Number of items
in "Doing" column is 3, and number of items in "Done" column is 2
C. WIP limit for Step X is 3. Step X is divided into "Doing" and "Done." Number of items
in "Doing" column is 2, and number of items in "Done" column is 1. One of the items in
the previous step is done and developer wants to move that item to Step X
D. WIP limit for Step X is 3. Step X is divided into "Doing" and "Done." Number of items
in "Doing" column is 4, and number of items in "Done" column is 0
E. WIP limit for Step X is 3. Step X is divided into "Doin - ANSWER - AD
Which of the following Framework/process model supports Agile Mindset? (select all
that apply)
1 point
A. Crystal
B. DSDM
C. Scrum
D. V-Model
E. Kanban
F. Lean Startup
G. Waterfall
H. XP
J. Sashimi - ANSWER - CEFG