What are some of the challenges with the Waterfall methods that prompted the software
industry to come up with alternatives like Agile? (select 2)
A. It is difficult to predict user/customer needs.
B. Incorrect interpretations of requirements by developers go undetected for a long time.
During user acceptance tests, these issues are discovered but it is very late.
C. Projects were very complex and big.
D. Projects cost too much. - ANSWER - AB
Which of following is valid on a Kanban Board? (select any 2)
A. WIP limit for Step X is 5. Step X is divided into "Doing" and "Done." Number of items
in "Doing" column is 3, and number of items in "Done" column is 1. One of the item in
previous step is done and developer wants to move that item to Step X
B. WIP limit for Step X is 3. Step X is divided into "Doing" and "Done." Number of items
in "Doing" column is 3, and number of items in "Done" column is 2
C. WIP limit for Step X is 3. Step X is divided into "Doing" and "Done." Number of items
in "Doing" column is 2, and number of items in "Done" column is 1. One of the items in
the previous step is done and developer wants to move that item to Step X
D. WIP limit for Step X is 3. Step X is divided into "Doing" and "Done." Number of items
in "Doing" column is 4, and number of items in "Done" column is 0
E. WIP limit for Step X is 3. Step X is divided into "Doin - ANSWER - AD
In Lean software development, what does the principle of "defer commitment" mean?
A. Decisions are made after having enough information from considering the
alternatives.
B. Decisions are made to choose the modern alternative.
C. Decisions are made just before a deadline.
D. Decisions are made to delay the product delivery to a later date. - ANSWER - A chưa
fix
In Lean software development, what does the principle of "deliver fast" mean?
A. Working alternatives are rapidly created.
B. A simpler version of software product (an MVP - Minimum Viable Product) is
developed first to reach the market rapidly.