Qsp Exam 2024/Latest Update /Actual 125 Exam Questions With Correct Verified Answers/ Graded A+ Guaranteed Pass

Document preview thumbnail
Preview 3 out of 28 pages

QSP EXAM 2024/LATEST UPDATE /ACTUAL 125 EXAM QUESTIONS WITH CORRECT VERIFIED ANSWERS/ GRADED A+ Guaranteed Pass When does the CGP apply? – Correct Answer-Any construction or demolition of one acre or more Activities under the CGP include: a. Routine maintenance to maintain original line and grade, hydraulic capacity, or original purpose of the facility. b. Disturbances to land surfaces solely related to agricultural operations. c. Clearing and grading 2 acres of land d. Discharges of storm water from areas on tribal lands. - Correct Answer-C A likely precipitation event is any weather pattern that is forecasted to have a ____% or greater probability of producing precipitation in the project area. a. 10 b. 25 c. 50 d. 75 e. 99 - Correct Answer-C A QSP is responsible for: a. Day to day implementation, inspections, and observations b. Amending the SWPPP as required c. Developing and certifying the SWPPP d. Certifying reports in SMARTS - Correct Answer-a. Day to day implementation, inspections, and observations 2 | P a g e QSP EXAM A storm that produces ½ inch or more of precipitation, with a 48 hour or greater period between rain events is a/an... a. Qualifying rain event b. Extended storm event c. Inactive storm event d. Unsafe monitoring event - Correct Answer-a. Qualifying rain event A temporary or permanent structural BMP that directs concentrated flows away from disturbed areas and prevents erosion is... a. erosion control b. run on/ run off control c. sediment control - Correct Answer-b. run on/ run off control Acceptable methods to demonstrate final stabilization include: a. 50%vegetative coverage b. 100% vegetative coverage c. RUSLE 2 method - Correct Answer-c. RUSLE 2 method Activities under the CGP include: a. Routine maintenance to maintain original line and grade, hydraulic capacity, or original purpose of the facility. b. Disturbances to land surfaces solely related to agricultural operations. c. Clearing and grading 2 acres of land d. Discharges of storm water from areas on tribal lands. - Correct Answer-c. Clearing and grading 2 acres of land All NAL data must be uploaded within ___ after NAL exceedance has been identified a. 24 hours b. 1 week c. 10 days d. 2 weeks 3 | P a g e QSP EXAM - Correct Answer-c. 10 days Certain non-storm water discharges may be necessary for the completion of construction projects. Therefore the General Permit authorizes such discharges provided they meet the following conditions except: a. Meet the NALs for pH and turbidity b. Not cause or contribute to a violation of water quality standards c. Comply with BMPs as described in the SWPPP d. Be infeasible to eliminate e. Causes or threatens to cause pollution, contamination, or nuisance - Correct Answer-e. Causes or threatens to cause pollution, contamination, or nuisance Hydrologic source controls are a design technique that minimize and/or slow the rate of stormwater runoff from the site. Examples include: a. Reduction of pervious surfaces b. Use of landscaping as a storm drain treatment feature c. Drain rooftop downspouts to impervious areas d. Stormwater treatment facility - Correct Answer-b. Use of landscaping as a storm drain treatment feature If the R Factor is ____, you can apply for the Erosivity Waiver. a. 1 b. Less than 1 c. 5 d. Less than 5 - Correct Answer-d. Less than 5 NEL Violation Reports must be submitted to State Board within 24 hours after exceedance has been identified. NEL's are only subject to: a. Risk Level 1 b. Risk Level 2 c. Risk Level 3 d. ATS Sites only - Correct Answer-d. ATS Sites only

Content preview

1|Page

QSP EXAM
QSP EXAM 2024/LATEST UPDATE /ACTUAL
125 EXAM QUESTIONS WITH CORRECT
VERIFIED ANSWERS/ GRADED A+
Guaranteed Pass
When does the CGP apply? –
Correct Answer-Any construction or demolition of one acre or more

Activities under the CGP include:
a. Routine maintenance to maintain original line and grade, hydraulic capacity, or original
purpose of the facility.
b. Disturbances to land surfaces solely related to agricultural operations.
c. Clearing and grading 2 acres of land
d. Discharges of storm water from areas on tribal lands.

- Correct Answer-C

A likely precipitation event is any weather pattern that is forecasted to have a ____% or greater
probability of producing precipitation in the project area.

a. 10
b. 25
c. 50
d. 75
e. 99

- Correct Answer-C

A QSP is responsible for:

a. Day to day implementation, inspections, and observations
b. Amending the SWPPP as required
c. Developing and certifying the SWPPP
d. Certifying reports in SMARTS

- Correct Answer-a. Day to day implementation, inspections, and observations

,2|Page

QSP EXAM
A storm that produces ½ inch or more of precipitation, with a 48 hour or greater period between
rain events is a/an...

a. Qualifying rain event
b. Extended storm event
c. Inactive storm event
d. Unsafe monitoring event

- Correct Answer-a. Qualifying rain event

A temporary or permanent structural BMP that directs concentrated flows away from disturbed
areas and prevents erosion is...

a. erosion control
b. run on/ run off control
c. sediment control

- Correct Answer-b. run on/ run off control

Acceptable methods to demonstrate final stabilization include:

a. 50%vegetative coverage
b. 100% vegetative coverage
c. RUSLE 2 method

- Correct Answer-c. RUSLE 2 method

Activities under the CGP include:

a. Routine maintenance to maintain original line and grade, hydraulic capacity, or original
purpose of the facility.
b. Disturbances to land surfaces solely related to agricultural operations.
c. Clearing and grading 2 acres of land
d. Discharges of storm water from areas on tribal lands. - Correct Answer-c. Clearing and grading
2 acres of land

All NAL data must be uploaded within ___ after NAL exceedance has been identified

a. 24 hours
b. 1 week
c. 10 days
d. 2 weeks

, 3|Page

QSP EXAM
- Correct Answer-c. 10 days

Certain non-storm water discharges may be necessary for the completion of construction
projects. Therefore the General Permit authorizes such discharges provided they meet the
following conditions except:

a. Meet the NALs for pH and turbidity
b. Not cause or contribute to a violation of water quality standards
c. Comply with BMPs as described in the SWPPP
d. Be infeasible to eliminate
e. Causes or threatens to cause pollution, contamination, or nuisance

- Correct Answer-e. Causes or threatens to cause pollution, contamination, or nuisance

Hydrologic source controls are a design technique that minimize and/or slow the rate of
stormwater runoff from the site. Examples include:

a. Reduction of pervious surfaces
b. Use of landscaping as a storm drain treatment feature
c. Drain rooftop downspouts to impervious areas
d. Stormwater treatment facility

- Correct Answer-b. Use of landscaping as a storm drain treatment feature

If the R Factor is ____, you can apply for the Erosivity Waiver.

a. 1
b. Less than 1
c. 5
d. Less than 5

- Correct Answer-d. Less than 5

NEL Violation Reports must be submitted to State Board within 24 hours after exceedance has
been identified. NEL's are only subject to:

a. Risk Level 1
b. Risk Level 2
c. Risk Level 3
d. ATS Sites only

- Correct Answer-d. ATS Sites only

Document information

Uploaded on
December 17, 2024
Number of pages
28
Written in
2024/2025
Type
Exam (elaborations)
Contains
Questions & answers
$24.99

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
JoyceWWales
3.9
(29)
Sold
154
Followers
18
Items
3758
Last sold
1 day ago



Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions