If the interior designer serves as the coordinator for construction drawings, what are her
responsibilities? - ✔✔1.) Directing & Coordinating consultant's work so the final set of construction does
represents a complete set of coordinated information. To do this they must:
a.) schedule regular meetings in exchange info and alert everyone in the progress of the job.
b.) progress prints should be exchanged between the consultants and the designer for ongoing
comparison of work being produced
c.) notify all consultants in writing of changes that occur.
d.) The designer must thoroughly check and coordinate all drawings before issuing bids or negotiating
the construction contract.
Describe the sequence which construction drawings are organized. - ✔✔1.) Title & Index Sheet -
includes project title, list of standard abbreviations and symbols used on the job, project data, & general
notes.(square footage, occupany category, etc...)
2.) Floor Plans - includes demo plan, finish plan, construction plan, telephone and power plan, and
furniture plan.
3.) Reflected Ceiling Plan(s)
4.) Elevations
5.) Details - millwork, glazing, ceilings, stairways and sometime structural details. Depending on the size
and complexity of project.
6.) Mechanical Drawings - includes HVAC & plumbing.
7.) Electrical Drawings (if required) - includes power and lighting, circuitry, specialty wiring (like fire
alarms), communication, and security systems
8.) Fire Protection (if required) - sprinkler plan
9.) Structural Drawings if needed.
What are the 4 different reference systems? - ✔✔1.) Title of Drawing - various reference symbols are
used to direct someone to the correct drawing.
2.) Elevation Reference Mark - placed on floor plan to indicate the elevation of the wall is somewhere on
set.
&Verified | 2024-2025 | 100% Score
If the interior designer serves as the coordinator for construction drawings, what are her
responsibilities? - ✔✔1.) Directing & Coordinating consultant's work so the final set of construction does
represents a complete set of coordinated information. To do this they must:
a.) schedule regular meetings in exchange info and alert everyone in the progress of the job.
b.) progress prints should be exchanged between the consultants and the designer for ongoing
comparison of work being produced
c.) notify all consultants in writing of changes that occur.
d.) The designer must thoroughly check and coordinate all drawings before issuing bids or negotiating
the construction contract.
Describe the sequence which construction drawings are organized. - ✔✔1.) Title & Index Sheet -
includes project title, list of standard abbreviations and symbols used on the job, project data, & general
notes.(square footage, occupany category, etc...)
2.) Floor Plans - includes demo plan, finish plan, construction plan, telephone and power plan, and
furniture plan.
3.) Reflected Ceiling Plan(s)
4.) Elevations
5.) Details - millwork, glazing, ceilings, stairways and sometime structural details. Depending on the size
and complexity of project.
6.) Mechanical Drawings - includes HVAC & plumbing.
7.) Electrical Drawings (if required) - includes power and lighting, circuitry, specialty wiring (like fire
alarms), communication, and security systems
8.) Fire Protection (if required) - sprinkler plan
9.) Structural Drawings if needed.
What are the 4 different reference systems? - ✔✔1.) Title of Drawing - various reference symbols are
used to direct someone to the correct drawing.
2.) Elevation Reference Mark - placed on floor plan to indicate the elevation of the wall is somewhere on
set.