CM 4211 Exam | 282 Questions Solved 100% Correct | Verified Solutions

Document preview thumbnail
Preview 3 out of 26 pages

CM 4211 Exam | 282 Questions Solved 100% Correct | Verified Solutions

Content preview

CM 4211 Exam | 282 Questions Solved 100%
Correct | Verified Solutions


"AGC" stands for American General Constructors? - ✔✔False



Private projects often require more supplementary information than public bids? - ✔✔False



An advertisement should say where and when the bid opening will occur? - ✔✔True



General conditions are conditions specific for a particular project? - ✔✔False



Supplementary conditions are conditions common for many projects? - ✔✔False



AIA form documents are not considered to be standard? - ✔✔False



Unless the contract says otherwise, on short-term projects progress payments are not owed? -
✔✔True



All government projects require bonds? - ✔✔True



Indemnification in the AIA General Conditions is considered intermediate? - ✔✔True

,The contract may give the owner the right to have disputes adjudicated in a different state
than where the project is located? - ✔✔True



Retention (retainage) is an amount kept by the owner from progress payments for the
express purpose of paying liquidated damages? - ✔✔False



Force Majeure means in the control of an entity? - ✔✔False



An escalation clause is used on short-term project? - ✔✔False



The differing site conditions clause will be found in the AIA index as such? - ✔✔False



How much time the contractor has to complete the project would be found in the
General Conditions? - ✔✔False



The changes clause is one of the threshold red flag clauses? - ✔✔True



The right of accessibility to the job site is not an implied obligation owed by the owner?
- ✔✔False



Liquidated damages are an agreed-upon amount per day for the contractor starting the
work late? - ✔✔False



The contract may give the owner the unilateral right to suspend the project? - ✔✔True



The contract may give the owner the unilateral right to terminate the project in whole or in
part? - ✔✔True

, The differing site conditions clause is not a threshold red flag clause? - ✔✔False



A Notice to Proceed tells the contractor when it can go on the site? - ✔✔True



Courts are not inclined to enforce such exculpatory clauses unless they are prominent, non-
ambiguous, and do not conflict with other contract provisions? - ✔✔True



A variation-in-quantities clause is for lump sum projects? - ✔✔False



Contractors prefer liquidated damages to actual damages? - ✔✔True



Threshold red flag clauses should be examined when the estimate is complete? - ✔✔False



A purchase order should not be used for a trash pickup contract? - ✔✔False



It is important to know whether sales taxes are in the quote from the supplier? - ✔✔True



A copy of the prime contract does not need to be given to a material supplier when using flow-
down language in the purchase order? - ✔✔False



A fabricator is usually considered a subcontractor and not a material supplier? - ✔✔False



"FOB supply house" means that the sale is complete when the truck is loaded at the supply
house? - ✔✔True



"FOB Jobsite" means that the material supplier will deliver the materials? - ✔✔True

Document information

Uploaded on
November 26, 2024
Number of pages
26
Written in
2024/2025
Type
Exam (elaborations)
Contains
Questions & answers
$13.49

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
KenAli
2.6
(18)
Sold
114
Followers
5
Items
24387
Last sold
1 week ago




Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions