DBIA CERTIFICATION TEST
Early Design and Construction - ANSWER A different form of DB
Designer (AE-1) is used for the RFP's bridging documents, which make up 20%
to 35% of the work.
It's possible to include both prescriptive and performance specs.
Design Standards for Design-Build - ANSWER A different form of DB
It has parameters but not answers.
Requirements Based on Performance
You can call it Design-Build to Budget.
What are the signs of Design-Bid-Build? PREscriptive Specs is the answer.
The lowest price at first
The schedule is not as important.
There are no legal obstacles
There Must Be Open-Selection
Things to Think About When Picking the Best Project Delivery Model -
ANSWER Effects on Stakeholders
The market situation
About the Owner
Needs for the Schedule
, Being Able to Change Your Mind
What Makes Design-Build Work? — ANSWER: Time to Finish is Very
Important
Requirements Based on Performance
Working together is important
Adaptability of Method
What makes CMAR unique - ANSWER CONSTRUCTION MANAGER AT
RISK [CMAR]
Specifications that tell you what to do
Early Involvement of the Builder
Want to Know About Costs Before DBB
Most of the time, faster than DBB
What Makes DB Projects Fail? — THE ANSWER CALL FOR FAILURE TO:
Build trust
Make sure everyone knows what their responsibilities and duties are.
Know about time, cost, and quality.
Commit While the design is being made
Three People Who Live in Design Build (DB)? CHOOSING AN ANSWER
SOURCE: How to Pick the Right Team, QBS
NEEDS: Accountability, Flexibility, and the Chance to Succeed
Early Design and Construction - ANSWER A different form of DB
Designer (AE-1) is used for the RFP's bridging documents, which make up 20%
to 35% of the work.
It's possible to include both prescriptive and performance specs.
Design Standards for Design-Build - ANSWER A different form of DB
It has parameters but not answers.
Requirements Based on Performance
You can call it Design-Build to Budget.
What are the signs of Design-Bid-Build? PREscriptive Specs is the answer.
The lowest price at first
The schedule is not as important.
There are no legal obstacles
There Must Be Open-Selection
Things to Think About When Picking the Best Project Delivery Model -
ANSWER Effects on Stakeholders
The market situation
About the Owner
Needs for the Schedule
, Being Able to Change Your Mind
What Makes Design-Build Work? — ANSWER: Time to Finish is Very
Important
Requirements Based on Performance
Working together is important
Adaptability of Method
What makes CMAR unique - ANSWER CONSTRUCTION MANAGER AT
RISK [CMAR]
Specifications that tell you what to do
Early Involvement of the Builder
Want to Know About Costs Before DBB
Most of the time, faster than DBB
What Makes DB Projects Fail? — THE ANSWER CALL FOR FAILURE TO:
Build trust
Make sure everyone knows what their responsibilities and duties are.
Know about time, cost, and quality.
Commit While the design is being made
Three People Who Live in Design Build (DB)? CHOOSING AN ANSWER
SOURCE: How to Pick the Right Team, QBS
NEEDS: Accountability, Flexibility, and the Chance to Succeed