Questions and 100% Solved Answers
Your installation is refurbishing an existing PES facility built in 1968. Do you need to
complete an ESSP? - ANSWER-Yes, and it requires DDESB approval.
As distance from the potential explosion site decreases, the potential for damage to an
exposed site from an explosion.... - ANSWER-increases.
Your installation is increasing the NEW for a storage site built in 1969 and storing a
hazard division that was not previously approved for that location. Do you need to
complete an ESSP? - ANSWER-Yes, and it requires DDESB approval.
Intraline distance (ILD) is the minimum distance permitted between... - ANSWER-two
operating buildings.
The purpose of an ESSP is to ensure safety, provide specifications, and... - ANSWER-
establish limits.
You must submit an ESSP for DDESB approval if the installation is... - ANSWER-
building an ES within an existing ESQD arc.
Failing to submit a successful ESSP may result in... - ANSWER-reduced operational
capacity.
Which are the phases of the ESSP process in order? - ANSWER-Development and
Evaluation, Submission, DDESB Review, and Implementation.
The Expedited Approval Request must... - ANSWER-explain why an expedited approval
is required.
Which part of the ESSP package contains background information, site location, and
the reason for the ESSP submission? - ANSWER-ESSP narrative
Which ESSP category addresses facilities and operations that do not completely
conform to deterministic QD criteria or meet the risk-based criteria in DESR 6055.09
Edition 1? - ANSWER-HSP
Which is NOT a common mistake when submitting an ESSP? - ANSWER-Sending the
ESSP to USATCES
Your facility does not have a lightening protection system (LPS). Which of these will you
have to submit? - ANSWER-Risk Assessment and command acceptance of the risk