CompTIA Project+ study test Questions and Answers (Latest Update 2025)

Document preview thumbnail
Preview 3 out of 21 pages

CompTIA Project+ study test Questions and Answers (Latest Update 2025)

Content preview

CompTIA Project+ study test Questions
and Answers (Latest Update 2025)
Which if the following MUST be clearly defined in a project
charter? - Correct Answer ✅Scope



Which of the following is the MAIN difference between an
open-ended and close-ended problem statement? - Correct
Answer ✅An open-ended problem statement leads to
multiple solutions while a close-ended one has limited
solutions



A project team member, Joe, has completed his project work.
Although the project is not completed yet, Joe has been
assigned by the PMO (Project Management Office) director to
a new project. Which of the following describes the
organization structure Joe works in? - Correct Answer
✅Project based



Which if the following is used to provide a functional
description if the efforts which are required in order to
accomplish a task? - Correct Answer ✅WBS dictionary



A project manager is entering the list of a project's activities
with their estimated begin and end time to visualize which

,CompTIA Project+ study test Questions
and Answers (Latest Update 2025)
activities overlap and when the project is scheduled to end.
Which if the following is the project manager building? -
Correct Answer ✅Gnatt chart



The project manager is sequencing a set of activities. They
discover that some of the activities may or may not occur
based on the outcome of other activities. Which of the
following is BEST suited in this situation to show the
activities' logical relationship? - Correct Answer ✅ADM
(Arrow diagramming method)



Which if the following is the MAIN difference between bottom
up and top down cost estimation? - Correct Answer
✅Bottom up leads to more accurate cost estimate than top
down because it is performed by subject matter experts



Which of the following purchasing processes should a project
team use to ensure that the work will be done per company
specifications, while selecting the overall cheapest provider? -
Correct Answer ✅RFP (Request for Proposal)

, CompTIA Project+ study test Questions
and Answers (Latest Update 2025)
One of the MAIN purposes of a kick-off meeting is to: -
Correct Answer ✅Assign and review roles and
responsibilities to the project team.



After the ground breaking at the new construction site, the
pile driving operation comes to a full stop due to the nature
of the terrain. Which of the following is MOST likely to occur? -
Correct Answer ✅The project manager must manage the
new issue as the project schedule could be delayed.



A new software solution is being deployed. The customer
realizes that an important piece of the software must be
purchased in order for the project to be successful. Which of
the following is TRUE about this scenario? - Correct Answer
✅Project schedule may be affected and the project manager
must follow the change control process.



While performing a scheduled walk through at a construction
site, the customer points out a discrepancy. Which of the
following is the FIRST step that should be taken before
submitting a change control form? - Correct Answer
✅Identify the change

Document information

Uploaded on
October 26, 2024
Number of pages
21
Written in
2024/2025
Type
Exam (elaborations)
Contains
Unknown
$13.49

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
Allivia
3.9
(147)
Sold
787
Followers
400
Items
15617
Last sold
1 day ago



Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions