What size lifts should be placed for bedding?
✓ 6" lifts
When should backfill not be placed next to a structure?
✓ When structure hasn't achieved 80% of it structural strength
Where does the elevation start on a footing?
✓ At the bottom
Each layer should be compacted to achieve what maximum density
percentage?
✓ 95%
What should be done to prep bedrock prior to placing footing?
✓ Grout should be placed to fill any voids in bedrock.
Master01 | September, 2024/2025 | Latest update
, 1 | P a g e | © copyright 2024/2025 | Grade A+
How far away should stockpiled material be away from an open excavated
hole?
✓ within 24"
What equipment is used to drive piles?
✓ 1. Gravity Hammers
✓ 2. Open-end and closed end - diesel hammers
✓ 3. Air and steam hammers
✓ 4. hydraulic Hammers
What is the wave equation for driving piles?
✓ between 2 and 10 blows per inch
When pre-boring when should you stop?
✓ within 5 feet of estimated pile tip
When do you check pile alignment?
✓ before the last 5' of the pile is driven