Clean Water Act - ANSWER Law set into place in 1970 for storm water regulation
NPDES - ANSWER Regulations for monitoring storm water activity on a construction
site, are outlined in
Immediately after project is awarded and before you begin any site work - ANSWER
When should you read and understand SWPP
Contaminated ground water - ANSWER What is not an allowable storm water discharge
or non-storm water discharge
When jurisdiction of operations specifies you can start - ANSWER When may
construction activity begin
303D list - ANSWER Waters that fail anti-degradation list are placed on which list.
An officer and project owner - ANSWER SWPPPs certification are signed by who
FALSE - ANSWER The document that must be completed signed and submitted to the
state to obtain authorization to discharge is the NOT. (T/F)
All construction has been completed both inside and outside - ANSWER NOT can be
filed when
is in charge of daily activities - ANSWER Operations on a construction site are the entity
in charge of plans and specification and the entity who?
Stay out of trouble with the law - ANSWER Motives for staying in compliance with storm
water objectives?
To protect and preserve beneficial use of U.S. waters, maintaining their clean, physical
and biological integrity - ANSWER Objectives of the clean water act are
National Pollutant Discharge Elimination System - ANSWER NPDES stands for