ARE 5.0 Practice Management Practice
Exam Questions with Correct Answers
What are the four reasons an architect should consider professional liability insurance? -
Answer✔✔-1. Social Responsibility, 2. Continuing Operations, 3. Contract Requirements, 4.
Business Survival
During the building of a pre-school and day care facility, the general contractor ran over the
allotted schedule which interrupted the client's intention to be up and running before the
beginning of the school year. The contractor is claiming that the delays are due to weather.
Where should the architect look for information to support or challenge the contractor's claim?
- Answer✔✔-Field Reports
Each project has a unique set of circumstances related to risk level. What are four typical ones?
- Answer✔✔-1. Client type, 2. standard-of-care, 3. financial, 4. project-delivery
Under what circumstances might you sign an operating agreement? - Answer✔✔-When forming
an LLC. (est. rules and guidelines)
Page 1/13
, EMILLECT 2024/2025 ACADEMIC YEAR ©2024 EMILLECT. ALL RIGHTS RESERVED FIRST PUBLISH OCTOBER, 2024
What examples of actions adhere to professional behaviors outlined for AIA members in the
Code of Ethics and Professional Conduct? - Answer✔✔-1. Provide pro bono services, 2. sign
drawings within responsible control, 3. advance sustainable design practices
What are some negative effects of falsely hiring an employee as a consultant? - Answer✔✔-1.
Loss of worker's compensation, 2. tax liabilities, 3. Lost employment benefit, 4. exposure to
fraud
According to AIA Document B1010, Standard Form of Agreement Between Owner and Architect
is required to carry which types of insurance? - Answer✔✔-1. Professional liability, 2. Workers'
Compensation, 3. Automobile Insurance, 4. General liability
What are the client risk probabilities an architect should ask themselves when writing a
proposal? - Answer✔✔-1. Client's expectations of error-free, near perfect drawings, 2. Client's
dreams exceed the reality of their funding, 3. Clients understanding of the construction process
What 4 project characteristics does a stipulated or lump-sum include? - Answer✔✔-1. Client has
extensive experience in the project type, 2. The project Scope is well-defined, 3. Hotel, hospital
or other project that has many units, 4. Client must have total fee before starting project.
What 2 things does an architect's professional-liability insurance cover? - Answer✔✔-1. Errors
by current employees, 2. Claims brought by third parties
What are typical purposes of a good, highly evolved professional training-and -development
program? - Answer✔✔-1. Ensures that employees are kept well informed of changing trends