Preliminary Design Build - answer A variation of DB
Uses Designer (AE-1) for the RFP's Bridging Documents that are 20%-35%
Design
Can include both Prescriptive & Performance Specs
Design Criteria Design-Build - answer A variation of DB
Includes parameters not solutions
Performance Based Requirements
Can be called Design-Build to Budget
What are Characteristics that lead to Design-Bid-Build? - answer
Prescriptive Specs
Lowest Initial Price
Schedule is Less Important
, Has no legal barriers
Open-Selection is Required
Factors to Consider When Making Decisions on Best Project Delivery Model
to Use - answer Impact on Stakeholders
Market Conditions
Owner Profile
Schedule Requirements
Ability to Make the Mental Shift
Characteristics That Lead to Design-Build ? - answer Completion Time is
Critical
Performance Based Requirements
Collaboration is Important
Flexibility of Approach
Characteristics of CMAR - answer CONSTRUCTION MANAGER AT RISK
[CMAR]
Prescriptive Specs
Early Constructor Involvement
STUDY with 100%
correct
answers(passed)
Preliminary Design Build - answer A variation of DB
Uses Designer (AE-1) for the RFP's Bridging Documents that are 20%-35%
Design
Can include both Prescriptive & Performance Specs
Design Criteria Design-Build - answer A variation of DB
Includes parameters not solutions
Performance Based Requirements
Can be called Design-Build to Budget
What are Characteristics that lead to Design-Bid-Build? - answer
Prescriptive Specs
Lowest Initial Price
Schedule is Less Important
, Has no legal barriers
Open-Selection is Required
Factors to Consider When Making Decisions on Best Project Delivery Model
to Use - answer Impact on Stakeholders
Market Conditions
Owner Profile
Schedule Requirements
Ability to Make the Mental Shift
Characteristics That Lead to Design-Build ? - answer Completion Time is
Critical
Performance Based Requirements
Collaboration is Important
Flexibility of Approach
Characteristics of CMAR - answer CONSTRUCTION MANAGER AT RISK
[CMAR]
Prescriptive Specs
Early Constructor Involvement