Miller Act - answer The existing federal law that required federal projects
exceeding 100k to require both a performance and a payment bond.
Created a legal separation between construction & Design
Delivery system, Type of Procurement and Type of Contract Format. -
answer What are 3 fundamental decisions an Owner must make when
initiating a feasible project?
Design Bid Build (Low Bid) - answer What is the most common project
delivery system?
The Owner - answer In traditional DBB delivery, who does the architect
sign their contract with?
None - answer What type of relationship does the contractor have with
an architect in Design Bid Build?
Scheduling Restraints or needs to be fast-tracked - answer Why would
you choose a Design Build delivery System?
Design Build - answer If the owner wants to shift risk to one party, what
project delivery method would they choose?
Design Build - answer What type of project delivery best suits a complex
project requiring close coordination of design and construction expertise?
1 - Joint Venture
, 2 - Integrated DB Firm
3- A/E Led
4 - Contractor Led - answer What are some forms of Design Build
entities?
Yes - answer Does the Owner bear risk in a design-bid-build?
1 - Linear project delivery
2 - Well defined and familiar relationships
3 - Benefit of Open Market Competition
4 - Owner is actively involved in design until documents are 100%
complete - answer What are some reasons owners choose DBB?
Limiting Factors to Design Build - answer 1 - Owner wants absolute
design control
2 - The programming limits flexibility and innovation
3 - The Owner cannot provide programming and performance
requirements.
Contractor Led - answer The most common DB entity structural
arrangement?
1 - Contractor
2 - Architect - answer What contracts does the owner holds in a CM @
Risk delivery method.
Qualifications and Best Price - answer How architect/engineering firms
are typically selected?
Sole Source/Direct Selection - answer A procurement option where the
DB'er is selected strictly on the basis of predetermined values and
qualification criteria already determined in consideration of reputation of
prior dealings with the owner? Often highly specialized.
100% correct
answers(passed)
Miller Act - answer The existing federal law that required federal projects
exceeding 100k to require both a performance and a payment bond.
Created a legal separation between construction & Design
Delivery system, Type of Procurement and Type of Contract Format. -
answer What are 3 fundamental decisions an Owner must make when
initiating a feasible project?
Design Bid Build (Low Bid) - answer What is the most common project
delivery system?
The Owner - answer In traditional DBB delivery, who does the architect
sign their contract with?
None - answer What type of relationship does the contractor have with
an architect in Design Bid Build?
Scheduling Restraints or needs to be fast-tracked - answer Why would
you choose a Design Build delivery System?
Design Build - answer If the owner wants to shift risk to one party, what
project delivery method would they choose?
Design Build - answer What type of project delivery best suits a complex
project requiring close coordination of design and construction expertise?
1 - Joint Venture
, 2 - Integrated DB Firm
3- A/E Led
4 - Contractor Led - answer What are some forms of Design Build
entities?
Yes - answer Does the Owner bear risk in a design-bid-build?
1 - Linear project delivery
2 - Well defined and familiar relationships
3 - Benefit of Open Market Competition
4 - Owner is actively involved in design until documents are 100%
complete - answer What are some reasons owners choose DBB?
Limiting Factors to Design Build - answer 1 - Owner wants absolute
design control
2 - The programming limits flexibility and innovation
3 - The Owner cannot provide programming and performance
requirements.
Contractor Led - answer The most common DB entity structural
arrangement?
1 - Contractor
2 - Architect - answer What contracts does the owner holds in a CM @
Risk delivery method.
Qualifications and Best Price - answer How architect/engineering firms
are typically selected?
Sole Source/Direct Selection - answer A procurement option where the
DB'er is selected strictly on the basis of predetermined values and
qualification criteria already determined in consideration of reputation of
prior dealings with the owner? Often highly specialized.