Twentieth Century Public contracting laws in North America have
historically mandated professional design services be purchased
separated from the selection of contractors solely on the basis of lowest
responsible bid. T or F? - answer True
Most Public Procurement statutes require the selection of design services
be purchased on the basis of lowest responsible bid? T/F? - answer False
There are always at least three parties involved in every project delivery
process; the Owner, Architect and Contractor. T/F? - answer True
It is recommended to get a contractor on board early during the business
and planning stage of a DB project to have the best opportunity to achieve
all objectives. T/F - answer True
The primary goal in choosing a delivery method is to ensure that it will
meet the Owner's project objectives while at the same time allowing the
project to be completed on time and within budget? T/F - answer True
CM @ Risk project delivery is faster than Design-Bid-Build, but can be
slower than Design-Build. T/F - answer True
Fast tracking a project and phased construction is possible using the CM @
Risk project delivery method. t/f? - answer true
The owner can pre-determine how a project's construction team will
interact with him or her and with each other through the selection of the
delivery system. T/F? - answer True
False with 100% correct
answers(passed)
Twentieth Century Public contracting laws in North America have
historically mandated professional design services be purchased
separated from the selection of contractors solely on the basis of lowest
responsible bid. T or F? - answer True
Most Public Procurement statutes require the selection of design services
be purchased on the basis of lowest responsible bid? T/F? - answer False
There are always at least three parties involved in every project delivery
process; the Owner, Architect and Contractor. T/F? - answer True
It is recommended to get a contractor on board early during the business
and planning stage of a DB project to have the best opportunity to achieve
all objectives. T/F - answer True
The primary goal in choosing a delivery method is to ensure that it will
meet the Owner's project objectives while at the same time allowing the
project to be completed on time and within budget? T/F - answer True
CM @ Risk project delivery is faster than Design-Bid-Build, but can be
slower than Design-Build. T/F - answer True
Fast tracking a project and phased construction is possible using the CM @
Risk project delivery method. t/f? - answer true
The owner can pre-determine how a project's construction team will
interact with him or her and with each other through the selection of the
delivery system. T/F? - answer True