2 disadvantages of using CPM are - correct answer ✔Complexity and
Required Commitment
Which of the following maps the entire construction process as a workflow? -
correct answer ✔Lean constructions
Lean Construction concepts have been adapted from the standards set in -
correct answer ✔Manufacturing
The chart that profides a micro view of the project is the - correct answer
✔Bar chart
A well prepared schedule will - correct answer ✔record progress and
documents problems
A SIPS is typically a schedule that covers - correct answer ✔2 to 4 weeks
well-developed project schedule reduces construction time, focus detailed
thinking, and - correct answer ✔Improve communication among the team
players
A time period when activities over lap is know as - correct answer ✔Lags
A wise Project Manager will use the 80/20 rule to - correct answer ✔decide
where is best spent