CON 1200 Exam with complete solutions
2024/2025
What defines performance-based acquisitions and describes required results in
clear, specific and objective terms with measurable outcomes? - ANSWER-
Performance Work Statement (PWS)
What establishes and defines all non-specification requirements for contractor's
efforts either directly or with the use of specific cited documents? - ANSWER-
Statement of Work (SOW)
What is the Government prepared document that states the overall performance
objectives and intend to provide maximum flexibility to offerors to propose an
innovative approach? - ANSWER-Statement of Objectives (SOO)
Government officials can generally meet one-on-one with potential offerors, as
long as no vendor receives preferential treatment. - ANSWER-True
Strategic market research takes a broad approach for conducting market
research. - ANSWER-True
What is the definition of bundling? - ANSWER-Consolidation of two or more
requirements, previously performed under separate smaller contracts, into a
single solicitation.
Within the DoD, a written Acquisition Plan is required for development programs
when the total cost of all contracts for the acquisition program has an estimated
value at, or exceeding, what value? - ANSWER-$10 million
2024/2025
What defines performance-based acquisitions and describes required results in
clear, specific and objective terms with measurable outcomes? - ANSWER-
Performance Work Statement (PWS)
What establishes and defines all non-specification requirements for contractor's
efforts either directly or with the use of specific cited documents? - ANSWER-
Statement of Work (SOW)
What is the Government prepared document that states the overall performance
objectives and intend to provide maximum flexibility to offerors to propose an
innovative approach? - ANSWER-Statement of Objectives (SOO)
Government officials can generally meet one-on-one with potential offerors, as
long as no vendor receives preferential treatment. - ANSWER-True
Strategic market research takes a broad approach for conducting market
research. - ANSWER-True
What is the definition of bundling? - ANSWER-Consolidation of two or more
requirements, previously performed under separate smaller contracts, into a
single solicitation.
Within the DoD, a written Acquisition Plan is required for development programs
when the total cost of all contracts for the acquisition program has an estimated
value at, or exceeding, what value? - ANSWER-$10 million