What are the three components that make up a project? Correct-1. Time
2. Money
3. Scope
What are the four principles to adhere to when designing base camps? Correct-1.
Scalability
2. Sustainability
3. Standardization
4. Survivability
What components are part of the superstructure of a nonstandard fixed bridge? Correct-
Everything above the supports (bearing plates and up):
Deck, railings, stringers
What components are part of the substructure of a nonstandard fixed bridge? Correct-
structural elements of the bridge below the bearing plates:
, Exam- ECCC General Engineering Test Questions and
Answers 100% Solved
Pier - supports the middle of the span
Wingwall - retaining wall that directs water away from the abutment
Abutment - what the span's ends rest on
What are the two levels of quality control? Correct-1. Unit QC (macro)
2. Project QC (micro)
Who is the only person who can alter a contract? Correct-Contracting officer (the KO)
How many days does standard concrete (Type 1A) take to cure? Correct-28 Days
What is the chemical reaction between water and Portland cement called? Correct-
Hydration